A Water Quality Impact Analysis of a Hydropower Facility
A low-head hydropower generating facility has been proposed at an existing dam site on a river. The state environmental agency has required an environmental evaluation into the potential...
Balancing Hydropower Development in the Ohio River Basin
A large number of retrofit hydroelectric projects have been proposed at existing navigation dams in the Ohio River basin. These proposals involve potentially adverse environmental impacts,...
Regional Rivers Resource Assessment as a Tool for Hydropower Planning and Policy: The Pacific Northwest Rivers Study
In August, 1984, the Bonneville Power Administration (BPA) and the Northwest Power Planning Council (Council) initiated a study to provide information about important river characteristics...
The Groundwater Studies for the Harrisburg Hydroelectric Project
The proposed Harrisburg Hydroelectric Project is a conventional 34.4-MW power facility located on the Susquehanna River in Harrisburg, Pennsylvania. The project will raise the river water...
HYOPS?Maximizing the Value of Your Hydro River System
This paper presents a microcomputer based software system, HYOPS, to optimize the operations of a series of hydro plants on a river system. The model can accommodate up to 10 plants which...
Optimization of Power Production Based on Efficiency Data
Computer programs dealing with different parts of the optimization process are in operation in Norway today, and they include: the hydrological part from weather forecast to reservoir...
Bonneville I Powerhouse Station Service Unit Rehabilitation
This paper presents the work being done towards the rehabilitation of the Bonneville I station service unit. The rehabilitation of this unit includes a generator rewind, excitation system...
Vertical Axis Hydro Turbines for Off Grid Installations
This paper describes the design, manufacture and testing of a 5 kW floating VAHT for use in tidal, ocean, and river installations. This work is based on the results of research contracts...
Retrofitting of Hydro Electric Generators with Bus Fed Solid State Excitation Systems
The Northern Hydro Division has completed retrofitting the excitation systems on 22 generating units ranging in output from 1 to 95 MWatts. The Big Creek Hydro Project upgraded these systems...
Hydroelectric Generator Rewinding Pitfalls and Means to Ensure Success
The failure or success of generator rewinding begins well before the actual rewind, and many of the pitfalls can be avoided if owners take some very important steps prior to the rewind...
Optimizing Joint Load Control for Hydroelectric Plants
This paper discusses a method to minimize water usage at a multi-turbine hydroelectric generating plant. At plants which do not spill water this optimization is directly converted to extra...
Electrical and Mechanical Design, Commissioning, and Performance of the Moose River Hydroelectric Project
The Moose River Hydroelectric Project is a single-unit run-of-river hydroelectric facility located near Lyonsdale, New York, and was developed by a private firm. The generating equipment...
Efficiency Monitoring Yields Large Revenue Gains
This paper presents a Washington Water Power Company program to increase hydroelectric plant operations' efficiency. This increase is due to improved flow, head, and megawatt...
Understanding Generator Static Excitation System
This paper explains some of the basic terms and features associated with a static excitation system (SES) to enable non-specialists to specify it according to their requirements. A simple...
Replacement of Computer Control at John Day Powerhouse
One of the first projects chosen by the Corps of Engineers for computer control was the John Day Project on the Columbia River. John Day powerhouse was completed in 1971 and has 16 generators...
Distributed Control Applications for Utility Hydroelectric Plants
In 1984, Washington Water Power began a program to improve monitoring and control systems for hydroelectric plants. The control systems being improved with distributed control equipment...
Programmable Logic Controller Based Governor/Plant Controller
This paper discusses the performance characteristics of the programmable logic controllers (PLC's) is based governor, particularly speed resolution and response times. The...
Uprating, Modernization and Automation of a Vertical Francis Turbine Generating Unit
The power demands of the Boise Cascade Paper Mill in Rumford, Maine are partially satisfied by two hydro-generating plants located in the near vicinity. In 1984 several factors prompted...
Computer Aided Design of Small Hydro Turbine?Phase II
Ateliers Bouvier have been expanding the use of its computer aided design (CAD) system during these last four years, and the aim of this paper is to present some additional aspects of...
Upgrading Open-Wheel Pit Hydro Plants with Modern Submersible Hydroturbines
This paper presents a new approach in rehabilitating open-wheel hydrosites by using modern, standard submersible hydroturbines, open flume type cylinder gates, and high efficiency draft...