Genesis of a Federal/Non-Federal Planning Study
This paper presents the course of action the Bureau of Reclamation undertook to develop an appropriate joint Federal/non-Federal planning process for a major pumped storage project. It...
Innovative Approach to New Water Supply/Power Development
Since the first deliveries made by the State Water Project (SWP) in the early 1960's the State of California has become known worldwide as a pioneer in the development of...
Piedra Del Aguila�New Hydropower for Argentina
Construction commenced in early 1985 on the 1. 0 billion Piedra del Aguila Hydroelectric Project on the Rio Limay about 1200 km (750 mi) southwest of Buenos Aires, Argentina. The project...
Evaluation of a Pump-Storage Hydropower Facility
This paper summarizes the findings of the evaluations conducted by faculty of the University of Missouri and outside consultants regarding the downstream effects of Harry S. Truman Dam...
Prospects for Hydroelectric Power Development at Corps of Engineer Dams
There are two basic approaches to developing hydroelectric power facilities at Corps dams. The Corps can develop projects at the request of Congress through the authorization process....
The Pacific Northwest Hydropower Data Base Study
The Hydropower Data Base is presently a functional tool for evaluating hydropower in the Northwest. It is a complete system which has been implemented using a variety of crosschecks and...
The Corps of Engineers' New Hydropower Manual
The Corps of Engineers has recently completed a new Engineering Manual (EM), which outlines procedures used for the evaluation of hydropower projects. It will serve as the basic Corps...
The Contribution of Local Area Management Teams Under Severe Environmental Conditions
This paper outlines a Westinghouse managed turnkey hydro electric project located in remote southwestern Wyoming near Kemmerer. The dam provides watershed control for the Hams Fork River,...
Construction of Yellowtail Dam & Power Plant 63-65
The Yellowtail Unit of the Missouri River Basin project is located on the Bighorn River in south central Montana. The key feature of the unit is Yellowtail Dam which rises 525 ft. between...
The Sand Bar Hydroelectric Project: A Case History
The Sand Bar project's major features include a reinforced concrete intake structure; 3. 5 miles of twelve foot diameter hard rock tunnel; a reinforced concrete powerhouse...
The Sultan River Hydroelectric Project
It took almost 70 years and required over 100 separate local, state and federal permits, but in June 1984, development of the Sultan River was finally completed for the multi-purpose use...
The Hrauneyjafoss Hydroelectric Project in Iceland
The Hrauneyjafoss Hydroelectric Project located in south central Iceland about 100 miles east of Reykjavik was constructed during 1978 to 1982. A maximum gross head of 295 feet is developed...
Power Development at Buffalo Bill Dam
Buffalo Bill Dam is on the Shoshone River in northwestern Wyoming near the city of Cody. The dam is a 325-foot-high concrete arch facility with a crest length of 200 feet. The dam was...
Grand Coulee Pumping/Generating Plant
The paper discusses the Grand Coulee Project history, including a brief review of landmark dates and events. Major general features of the Project are covered, including civil works, mechanical...
Economic Analysis of Hydroelectric Projects
This paper deals with specifics and refinements that develop 'rules of thumb' for analysis of hydro projects. The authors' experience is on sites...
Power Value Determinations
Past and current federal methodology and procedures in power value determinations are presented for consideration by Western Area Power Administration (Western), U. S. Department of Energy...
Economic Analysis of Low Head Hydropower Projects
A typical low head hydropower project is described and used as an example of the effect of tailwater on power generation. The discharge characteristics of upstream facilities, pool regulation...
Hoover Dam Planning, Financing and Repayment
After the original conception of the 'Boulder Canyon Project,' and in the first stage of the work, complete designs and specifications were prepared for the dam,...
Impact of Economic Factors on Development of the Lower Euphrates Basin in Turkey
The case of Lower Euphrates in Turkey represents fairly well the dynamic character of multi-purpose projects with respect to technological developments and changes in economic factors....
Insuring Security Requirements of Power Contracts
Under the fixed, or levelized rate utility contract, utility offers a fixed rate for the life of the contract. In the early years, the rate is in excess of the utility's avoided...
Return to search