Movable Dam?Gate Selection Procedure
Very few new dams are now being considered, particularly for waterpower and even more specifically for low head waterpower in the lower reaches of major rivers. The City of Harrisburg,...
Licensing and Relicensing After the Electric Consumers Protection Act of 1986
Recent changes in the Federal Energy Regulatory Commission (FERC) regulations and subsequent, substantive legislative changes have produced a shift in emphasis in the licensing/relicensing...
Case Study on the Development of a Hydro License Compliance Monitoring System
As the holder of 29 Federal Energy Regulatory Commission (FERC) licenses, Pacific Gas and Electric Company (PGandE) has an obvious need to monitor and document compliance with the numerous...
Licensing a Hydroelectric Power Plant at Navajo Dam
A hydroelectric power plant at the base of Navajo Dam was envisioned by the Bureau of Reclamation and the Bureau of Indian Affairs to support the development of the Navajo Indian Irrigation...
Marketing a Public-Private Small Scale Hydro Project: Case History, Kent County, Michigan
In 1982, Kent County, Michigan faced an interesting dilemma. Back in 1965, they had purchased the Fallasburg Dam and powerhouse from Consumers Power Company for 1. Without putting funds...
Feasibility of Cold Water Releases from Lake Britton
The Pit River in Shasta County, California, is the site of the Pit 3, 4 and 5 Project, a major hydroelectric facility operated by the Pacific Gas and Electric Company (PGandE) under Federal...
A Case Study of Hydropower Operation Based on Runoff Forecast
The intent of this paper is to outline a forecast approach developed to enable the operation of power storage projects, and to illustrate from employing the approach that overall system...
Stochastic Optimization of Reservoir Systems Operations
This paper addresses the stochastic optimization of real-time monthly operations of multi-reservoir systems by Dynamic Programming. A two-stage optimization framework that consists of...
DURAPLOT: A Flexible Approach to Hydropower Site Optimization
The U. S. Army Corps of Engineers, North Pacific Division Office has over the past six years performed reconnaissance and feasibility level hydropower studies at a variety of sites throughout...
Status and Prospectives of Small Hydro Power Development in Egypt
The paper describes the current status of hydropower development in Egypt and its future prospects. Emphasis is made on reviewing the potentialities for small, mini and micro-hydropower...
Early Detection of Rotor Cracks?Monitoring & Methodology
This paper describes a diagnostic method for the early detection of shaft cracks on rotating machines. The method is based on interpretation of the lateral synchronous (1x) and twice per...
Case Study: Siphon Penstock Operations
Hydroelectric power plants utilizing siphon penstocks operating near Winter, Wisconsin and at Jim Falls, Wisconsin have met or exceeded expectations after fine tuning of the vacuum and...
The Role of Model Studies in Add-On Hydro Projects
The reasons for modeling add-on projects are reviewed, and guidance given for the process of determining, first, the need for modeling, and second, if modeling is necessary, whether physical...
Pontook Hydroelectric Project?A Turnkey Case Study
This paper is presented in two parts. The first, presented by B. H. Adams, gives a general overview of the Pontook Project including major physical features and the financed turnkey approach...
Economic Evaluation of Replacement Turbine Runner Bids
Many owners of hydro facilities are investigating increasing plant capacity and output by upgrading existing hydraulic turbines. Typically, the owner will conduct a detailed feasibility...
Potential for Upgrading the Robert Moses Niagara Power Plant
This paper summarizes the feasibility of increasing the generating capacity of the Robert Moses Niagara Power Plant by replacing the turbine runners, upgrading the generators, and replacing...
Tracer Dilution Flow Measurement Application to Short Penstock Length
Absolute performance evaluation of hydro-turbines requires the determination of flowrates. Flow measurement is probably the most difficult aspect of determining a unit's efficiency....
Design and Commissioning of the Philadelphia Hydroelectric Project
The Philadelphia Hydroelectric Project consists of a single horizontal-shaft double-regulated S-type unit, rated 3440 kW, utilizing a programmable controller for unit operation together...
Digital Control of 180MW Francis Turbines: Controller Design, Simulation, and Operational Results
The features of a new hydro-power station are outlined as are some specifications that the customer required of a digital controller. Both hardware and software aspects of this recently...
Upriver Dam Hydroelectric Project Rehabilitation After Failure, Part B: Rehabilitation and Enhancement of Project Civil and Mechanical Facilities
A feasibility investigation of rehabilitation alternatives was conducted which identified several alternatives for repairing the damage and placing both powerhouses back on-line. These...
Return to search