Weak Rock in Two Rockfill Dams
Two South Australian concrete face compacted rockfill dams, built from soft rock won from each dam site, have performed successfully in service with only small leakage and settlements...

Concrete Face Rockfill Dams of the Winneke Project
Two of the three dams forming the Winneke Reservoir, near Melbourne, Australia, are concrete face rockfill dams. A minor dam forming the sludge storage pond for the project's...

The R. D. Bailey Dam, a Concrete-Faced, Earth-Rockfill
A case history for the R. D. Bailey Dam, describing its comparatively unique design and construction considerations, and its operational performance since initial reservoir filling in...

Mangrove Creek Dam: Use of Soft Rock for Rockfill
Mangrove Creek Dam is an 80 m high concrete faced rockfill dam (CFRD) completed in 1981. The embankment was constructed largely out of low strength sandstones and siltstones available...

Fortuna Concrete Face Rockfill Dam
The Fortuna Dam is a 60 m high concrete face rockfill dam located in Panama, designed to be built in two stages. This paper describes the construction of the first stage dam, 60 m high,...

Boondooma Dam
Concrete faced rockfill construction was adopted for the 210 ft (64 m) high Boondooma Dam in Southern Queensland, Australia, after detailed comparison between concrete faced and earth...

Khao Laem?A Concrete Face Rockfill Dam on Karst
A continuously reinforced concrete faced rockfill dam has been successfully designed and constructed on a karstic limestone foundation in Central West Thailand. The dam is not in an earthquake...

Design of Concrete-Faced Rockfill Dams
Design principles adopted in 1966 by the Hydro-Electric Commission have been applied to nine concrete-faced rockfill dams and remain substantially unchanged. Experience shows that the...

Construction of Concrete Face Rockfill Dams
The Hydro-Electric Commission, Tasmania, Australia has been building concrete face rockfill dams since 1968. Eight dams from 26m to 110m high have been completed, and the highest at 122m...

Design and Stability Evaluation of Balsam Meadow Dam
The proposed Balsam Meadow Dam is a 126 feet high concrete-faced rolled rockfill dam currently under construction for the Balsam Meadow hydroelectric project in California. Detailed field...

A Study of Deformations in Concrete Faced Rockfill Dams
This paper presents the results of studies on the behavior of certain concrete faced rockfill dams (CFRD), which were conducted during the Basic Design of Machadinho dam in Brazil. The...

The Xing? Rockfill Dam
The concrete-face rockfill dam of the 5,000MW Xingo Hydroelectric Project in Brazil, is at the bidding stage at the present time. The dam has a maximum height of 460 ft (140m) and the...

Segredo Dam: Basic Design Aspects
Segredo dam, located immediately downstream of Foz do Areia in the Iguacu river, Parana, Brazil, is the next concrete face rockfill dam to be built by 'Companhia Paranaense...

Machadinho Dam in Brazil
This paper presents the reasons for selection of a concrete-face rockfill dam for Machadinho Hydroelectric Project in Brazil. It also describes the main characteristics of the dam, as...

The Design of Macagua Concrete Face Rockfill Dam
This article describes the design characteristics of the concrete face rockfill dam at Macagua, which will have a total length of about 9,200 ft (2,800 m), an average height of 66 ft (20,0...

The Upstream Zone in Concrete-Face Rockfill Dams
The upstream zone of small rock, the supporting zone for the slab at many recent concrete-face rockfill dams has contained less than 20% of particles smaller than the No. 4 sieve. Such...

Design of Cirata Concrete Face Rockfill Dam
The Cirata Hydro-Electric Project on the Citarum River in Western Java, Indonesia is at present under construction for Perusahaan Umum Listrik Negara (PLN). The project which is being...

Concrete Face Rockfill Dams?Design, Construction, and Performance
Concrete face rockfill dams are being used with greater frequency and to greater heights in the last decade. The developments leading to this progress are many and are addressed in the...

The Sand Dam
Currently under construction is the 443 ft. high sand fill dam. Being erodible, pervious and liquefiable, sand would normally be considered as n unsuitable material to construct LaVueltosa...

Logan Airport Re-Visited
The first detailed evaluation of self-weight consolidation of a large hydraulic clay fill was performed during the construction of Logan Airport in Boston nearly 40 years ago. The paper...

 

 

 

 