Design and Operation of a Differential Surge Tank
The differential type of surge tank is more effective in operation than the simple type because it reacts more quickly to load changes of all sizes. The differential tank is also usually...
Long Lake Dam Model Studies
The Long Lake spillway was designed at the turn of the century as a standard ogee section with an upstream batter for a maximum head of 179 feet (55 m). It did not include any energy dissipator....
Mountain Jungle Intakes?Design and Model Study
Nine intakes of various sizes and designs supply water to the two high head power plants in the Sungai Piah Hydroelectric Development in Malaysia. The intakes are located on steep mountain...
The Role of Model Studies in Add-On Hydro Projects
The reasons for modeling add-on projects are reviewed, and guidance given for the process of determining, first, the need for modeling, and second, if modeling is necessary, whether physical...
Hydropower at Navigation Projects
Hydropower at navigation projects has been found to be compatible with the intended use of the project; however, it is important for the hydropower developer and the project owner to be...
Layout of a Powerhouse Adjacent to Lock and Dam Structures
An approach flow to a powerhouse intake adjoining existing lock and dam structures may cause a significant reduction in the efficiency of the powerhouse and give rise to an economically...
Low Head Hydraulic Model Justifies Cost
In many cases, developers of low head hydroelectric plants fail to use physical hydraulic modelling as a tool in the design process. Economic constraints are often cited as the primary...
Model Studies for Potential Modification of Pardee Spillway
East Bay Municipal Utility District, a public water supply agency in the San Francisco Bay Area, is examining the spillway adequacy of its primary water supply reservoir. Flood routing...
Flow Calculation in a Francis Runner
The flow through a Francis runner has been analysed theoretically. The flow calculations have been carried out by use of an inviscid 3D computational method solving the Euler-Equations....
The Value of Model Testing in Computer Aided Pump and Turbine Design
This paper discusses the importance of model testing for development and sharpening of interpretive techniques through which computational codes can be effectively used for the design...
Rehabilitation of a High Specific Speed Francis Turbine
An upgrade of two (2) 4. 06 meter diameter high specific speed Francis turbines is now in progress. These machines were originally installed by Allis-Chalmers in the 1920's...
Racine?5 Years of Successful Operating Experience with the World's Largest Bulb Turbines
In September 1982 two bulb turbine generating sets with a runner diameter of 7700 mm and a generator rating of 25 MVA were put into commercial operation at the Racine dam on the Ohio river....
Computer Aided Design of Butterfly Inlet Valves
Computer simulation of butterfly inlet valves (throughflow, lattice) in hydropower schemes is presented. The software is intended for practisting engineers to obtain significant parameters...
Competitive Model Testing for Replacement Runners at the Wells Hydroelectric Project
The Wells Hydroelectric Project, located on the Columbia River, contains ten Kaplan-type turbines, each rated at 123,000 HP (91,720 kW) at a net head of 64. 9 ft. (19. 8m). The plant has...
Experimental Investigation of the Cross Flow Turbine
A laboratory model of the Cross Flow Turbine was investigated in the Hydraulics laboratory of Colorado State University. Because of the successful use of this turbine in the developing...
An Integrated Site Controller-Network Monitoring System for Small Scale Hydroelectric Sites
Over the past decade more and more small scale hydroelectric power developers have faced the question of the economic feasibility of installing microprocessor based control systems for...
Pyrites Hydroelectric Project, Canton, New York
This paper describes the Pyrites Hydroelectric Project in Canton, New York, an 8-MW project completed in December 1985. The key to its successful development was a team approach that included...
Grout Supports Brooklyn Tunneling
At the Red Hook project in Brooklyn, microfine cement grout was injected from the surface to support underground tunneling. The hand-dug tunnel was built to connect to sewer pipes. Subsurface...
A Station With a View
The Port Authority TransHudson Corp. (PATH) is renovating and expanding Exchange Place station, the first stop in New Jersey across the Hudson River from lower Manhattan. To be completed...
Subsurface Savings
Less conservatism than usual in designing building foundations is being accepted or demanded by some owners to save money. The article describes four examples of cost-cutting innovations,...