Design Improvements on a Small Hydro Project
The Whiskeytown Hydroelectric Project, built for the City of Redding, California, provides an excellent example of the type of improvements in general arrangement which can be achieved...

Hydropower Development at North Hartland Lake, Vermont
The purpose of this paper is to give a short history of the first hydropower development by non-Federal interests at a Corps of Engineers flood control dam and reservoir within the jurisdiction...

Small Hydrodevelopment: An Owners Perspective?El Vado, New Mexico Hydroelectric Project
The construction of the El Vado Hydroelectric Project posed several unique problems. The joint ownership of the dam between a Federal and State agency was unique to the region. The proposal...

Summer Falls High Head Kaplan Turbine Project
The Summer Falls Project is located on the Main Canal of the Grand Coulee Irrigation Project approximately eight miles south of Coulee City in Grant County, Washington. The power development...

Our Municipal Water System Has Power
Hydroelectric potential exists in the Boulder, Colorado municipal water system. Excess pressure is developed in the water system because the water originates in the Rocky Mountains, west...

Hydropower Goes Downtown
Beneath a busy street in Southern California seems an unlikely location for a small hydroelectric generating plant. However, located just below El Segundo Boulevard in the town of El Segundo...

Pyrites Hydroelectric Project, Canton, New York
This paper describes the Pyrites Hydroelectric Project in Canton, New York, an 8-MW project completed in December 1985. The key to its successful development was a team approach that included...

Grout Supports Brooklyn Tunneling
At the Red Hook project in Brooklyn, microfine cement grout was injected from the surface to support underground tunneling. The hand-dug tunnel was built to connect to sewer pipes. Subsurface...

Roller Compacted Concrete Mix Design for Pamo Dam
Pamo Dam is designed as a 265 foot (81M) high gravity dam that will be located on the Santa Isabel Creek in San Diego County, California. RCC volume will be approximately 491,000 cubic...

Evaluation of Cores From Two RCC Gravity Dams
Galesville Dam, Oregon, completed in August 1985, and Upper Stillwater Dam, Utah, completed in August 1987, are two RCC (roller compacted concrete) gravity dams featuring different approaches...

Design and Construction of Lower Chase Creek Dam
Lower Chase Creek Dam is a roller compacted concrete flood control dam located in a generally dry creek in eastern Arizona. Dam design, including the site investigation and start-up of...

Construction of Elk Creek Dam
Construction of Elk Creek Dam, located in Southwest Oregon, is currently underway with completion scheduled for September 1988. The main dam contract was awarded to Ohbayashi Gumi Ltd....

Construction of Upper Stillwater Dam
This paper describes the equipment, placing methods, and peak production rates from the contractor's viewpoint for both the Roller Compacted Concrete and the Slipformed Facing...

Roller Compacted Concrete Design for Urugua-I Dam
Gravity dam construction by the roller compacted concrete method (RCC) has received widespread interest following completion of Shimajigawa Dam in Japan (1981) and Willow Creek Dam in...

RCC Storage Pads at Tooele Army Depot, Utah
Two 30. 5 m (100 foot) by 91. 4 m (300 foot) ammunition storage pads, each 381 mm (15 inches) thick, were constructed by the Sacramento District of the U. S. Army Corps of Engineers in...

Exploration of Karst Conditions in Central Florida
Walt Disney World, which comprises some 28,000 acres (11,000 ha) in central Florida, is underlain by cavernous limestone and is characterized by karst topography; with distinct low ground...

Evaluation of Reservoir Seepage in Karst Topography
Areas where seepage is likely to occur in the karst environment of the proposed West County Reservoir, Roanoke County, Virginia have been indentified. Solutioning exists in the form of...

Geotechnical Exploration and Site Preparation Techniques for Large Mall in Karst Terrain
A large commercial mall and secondary developments were planned for construction in a karst area near Clarksville, Tennessee. A geotechnical exploration was conducted to evaluate the occurence...

Treatment of Karst Along Tennessee Highways
The construction and maintenance of highways in karst areas of East Tennessee has resulted in the occurrence and treatment of induced sinkholes along the ditchlines of numerous highways....

Foundation Treatment of Karstic Features Under TVA Dams
TVA has constructed many of its dams on limestone foundations. Some of these foundations have been highly weathered and required special treatment not only to ensure strength but to develop...

 

 

 

 

Return to search