Advance Prediction of Flow-Induced Variations
Frequency analysis of hydraulic vibrations has been applied using a transfer matrix and impedance method. The computer program is given for the self-excited and forced vibrations, together...

Open Flume Turbine Intake Geometry
An inexpensive physical hydraulic model was used to investigate the geometry of two different open flume turbine intakes. One intake utilized an inverted, fabricated pump bell type of...

Diffuser Performance for Draft Tube Applications
Available information on diffuser performance is summarized in relation to draft tube applications. This paper is particularly directed at the implications of basic research with these...

Hydraulic Machines Model Acceptance Tests
The article begins with a description of the modern test installations, giving the dimensions of the models most frequently used and the head heights. Attention is then given to the most...

Sherman Island Hydro Cofferdam
The design and construction of an eight hundred foot long by sixty-five foot high cofferdam is discussed. The cofferdam was located to permit major renovation of the existing downstream...

Arch Dams for Small Hydroelectric Sites
Approximate formulas are developed for the design of small arch dams. These designs, although conservative, frequently allow for economies over other dam types. Considered are: an approximate...

Conventional Machinery/Unconventional Applications
The U. S. Bureau of Reclamation has become increasingly involved in small-scale hydroelectric projects involving unconventional applications for conventional hydraulic machinery. One ongoing...

Nanpil River Hydropower Project Pohnpei, Federated States of Micronesia
The Nanpil River Hydropower Project is a 1600 KW run-of-the-river hydropower project located on the tropical island of Pohnpei, Federated States of Micronesia. The hydropower project will...

An Overview of Hoover Dam Tunnel Spillway Damage
The Hoover Dam tunnel spillways have provided the Bureau of Reclamation hydraulic laboratories with new and continued opportunities for applied research. During the peak years of the Boulder...

Modernization of Existing Hydroelectric Power Stations in Conjunction with Conversion to Automatic Operation
The easiest and, in the long run, the least expensive method in most cases is the installation of an electronic turbine governor that is not only easy to incorporate in the power station...

Experiences During Overhaul of Hydroelectric Units
This paper describes some of the conditions found during major overhaul of main units at two hydroelectric power plants. Problems encountered and their solutions are described. The effects...

More Kilowatts with Less Investment
The paper discusses partial or complete modernization of hydraulic units and/or governing system as a means to increasing profitability. A combination of general and case history applications...

Analysis of Expanding the Wolf Creek Powerplant
The Nashville District, Corps of Engineers, is examining the feasibility of expanding the Wolf Creek powerplant to increase its peaking capability. The economic analysis of peaking expansions...

Application of Computer Aided Design and Analysis Tools for Upgrading Existing Power Plant Equipment
This paper presents examples where state-of-the-art computer aided design and analysis techniques have been applied to upgrade hydraulic performance and structural reliability of existing...

Synopsis: Ozark-Webbers Falls Turbine Repairs
The Ozark and Webbers Falls powerhouses were designed and constructed under the supervision of the U. S. Army Corps of Engineers and are located on the McClellan-Kerr Arkansas River Navigation...

Competitive Model Testing for Replacement Runners at the Wells Hydroelectric Project
The Wells Hydroelectric Project, located on the Columbia River, contains ten Kaplan-type turbines. The plant has been in commercial operation since January, 1969. The runners have a long...

Application of an Integrated Numerical System for the Modernization of Hydro Turbines
The modules of an integrated numerical system for the new design and replacement of hydro power plant components are described and some examples of application are shown. The main modules...

Rehabilitation of a Pump/Turbine
Between 1964 and 1968, eight 212 in pump discharge diameter Baldwin-Lima-Hamilton vertical pump/turbines with Westinghouse motor/generators were installed in Philadelphia Electric Company's...

Uprating Francis Turbines Provides Additional Energy
The use of existing powerhouse, penstocks, dams and unit configuration, all provide for a quick cost effective method to increase output from an existing turbine installation. This paper...

Uprating Hydro Turbines and Generators
Various engineering evaluations of the turbine and generator components are required when considering uprating units. Often, certain turbine and generator components have to be redesigned...

 

 

 

 