Synopsis: Ozark-Webbers Falls Turbine Repairs
The Ozark and Webbers Falls powerhouses were designed and constructed under the supervision of the U. S. Army Corps of Engineers and are located on the McClellan-Kerr Arkansas River Navigation...

Siphon Penstock?An Economic Way to Develop Hydros
As part of the 48 MW Jim Falls Hydro Redevelopment Project by Northern States Power Company, a minimum flow powerhouse was constructed with a siphon penstock. The Minimum Flow Unit (MFU)...

Competitive Model Testing for Replacement Runners at the Wells Hydroelectric Project
The Wells Hydroelectric Project, located on the Columbia River, contains ten Kaplan-type turbines. The plant has been in commercial operation since January, 1969. The runners have a long...

Application of an Integrated Numerical System for the Modernization of Hydro Turbines
The modules of an integrated numerical system for the new design and replacement of hydro power plant components are described and some examples of application are shown. The main modules...

Rehabilitation of a Pump/Turbine
Between 1964 and 1968, eight 212 in pump discharge diameter Baldwin-Lima-Hamilton vertical pump/turbines with Westinghouse motor/generators were installed in Philadelphia Electric Company's...

Uprating Francis Turbines Provides Additional Energy
The use of existing powerhouse, penstocks, dams and unit configuration, all provide for a quick cost effective method to increase output from an existing turbine installation. This paper...

Uprating Hydro Turbines and Generators
Various engineering evaluations of the turbine and generator components are required when considering uprating units. Often, certain turbine and generator components have to be redesigned...

Assessment of Probable Fishery Impacts of Hydroelectric Development at Lock and Dam No. 26 (Replacement), Mississippi River
Early coordination with affected Federal and state agencies allowed completion of an Environmental Assessment for a hydroelectric plant proposed for Lock and Dam No. 26 (Replacement)....

Galt Energy's Inverted Siphon System
Galt Energy Systems' involvement with attempting to standardize the civil component began with studies at small remote sites in Northern Ontario. The system design evolved...

A New Generation of Standard Francis Spiral Turbines
A new generation of standardized Francis spiral case turbines has been developed by Voith. The high performance has been achieved through employment of the most recent hydraulic designs...

Transient Analysis of Variable Geometry Turbines
An interactive general purpose hydraulic transient computer simulation procedure is presented which is capable of performing transient analysis of variable geometry turbine installations....

Simplified Model for Micro-Hydro Feasibility
A computer model was developed for evaluating the preliminary hydraulic and economic feasibility of potential micro-hydro development sites. Among the main objectives of the model are...

Design of Tension Member Insulated Anchor for Arctic Pipelines
This paper explores the latest development in above-ground waterflood pipe anchors currently being used on the SOHIO operated portion of the Prudhoe Bay Oil Field. The objective of the...

Anchorage Taps Eklutna Lake for New Water Supply
The 170 million Eklutna Water Project will furnish water to Anchorage, Alaska by the summer of 1988. The project consists of an 8,500-foot long diversion tunnel, 6 miles of 54 to 60-inch...

An Overview of Cold Region Considerations for the Design of the Eklutna Water Project
The paper presents a brief overview of cold regions considerations that were considered during the design of the various elements of the Eklutna Water Project in Anchorage, Alaska. The...

Alyeska Reroutes Trans-Alaska Pipeline at MP 200
This paper discusses the 1985 wintertime repair/reroute to the Trans Alaska Pipeline System (TAPS). The rerouted pipe was approximately 4000 feet long and cost approximately 27 million....

Upper Delaware River Ice Control?A Case Study
During February 1981 a castastrophic breakup ice jam occurred along a reach of the Delaware River near Port Jervis, NY, causing 14. 5 million in damages. In February 1982 another breakup...

Systems Model for Water Supply Following Earthquakes
The water supply for San Francisco is described with emphasis on the city's auxiliary water distribution network, which provides fire protection for the most heavily built-up...

Earthquake Risks to Utah Water and Gas Systems
Designed to guide local earthquake hazard reduction programs, this study estimates direct aggregate earthquake damage to Davis and Salt Lake County utilities. For making these loss estimates,...

The Effects of the 1985 Mexico City Earthquake on Underground Water & Sewer Pipelines
The 1985 Mexico City Earthquake left thousands dead and many thousands more without shelter. The visible damage was immense and terrible, and familiar to people around the world through...

 

 

 

 