A Case Study: Relicensing of Pensacola Hydropower Project
The current license for the Pensacola Hydropower Project (orginally licensed in 1939) will expire in 1988. The relicensing process for the project currently is underway. During the consultation...

Effects of Selective Withdrawal and Hypolimnetic Releases on Downstream Fish Resources
Selective withdrawal (multilevel outlet) structures on dams can be operated to modify reservoir discharges with the goal of improving downstream water quality and fish resources. A study...

Cumulative Impact Assessment: Application of a Methodology
The authors expanded upon the Federal Energy Regulatory Commission's (FERC) Cluster Impact Assessment Procedure (CIAP) to provide a practical methodology for assessing potential...

Field Experiences in Improving Water Quality Downstream From Dams
Recent experiences by the Tennessee Valley Authority in improving water quality and fish habitat downstream from dams are presented. At Douglas Dam, floating pumps near the surface of...

Reservoir Releases Improvements?Requiem for Integrating Pollution Control and Resource Management Programs?
To better define the interrelationships between economic growth and development, pollution control, and water resource management, TVA conducted two studies that examined how reservoir...

The Impact of Inlet Flow Characteristics on Low Head Hydro Projects
This paper discusses the intake civil designs, addressing head loss and flow distribution into the turbine intake. The impact of poor flow quality on head losses, turbine performance,...

Application of Split Roller Bearings in Small Vertical Hydro Turbines
The elimination of lower turbine bearing problems with regard to reliability and water flow contamination was the main concern of this project. A design was needed that would fit the existing...

Control and Tests of Tims Ford Induction Generator
This paper will discuss the electrical control scheme and commissioning tests developed for a small induction generator installed by the Tennessee Valley Authority (TVA) at its Tims Ford...

Quality Control/Inspection�Upper Stillwater Dam
Roller compacted concrete construction, or RCC, is a relatively new method of constructing concrete dams and involves placing and spreading no-slump concrete in horizontal layers and compacting...

Quality of Works in RCC in France: A Contractor's Solution
Bec Freres S. A. , a French dam contractor, introduced the technique of roller compacted concrete (RCC) into France. The first two French RCC dams were built as a result of a program of...

RCC Pavement Construction and Quality Control
In October 1986 a 16,500 sq yd (14,300 sq m) roller-compacted concrete (RCC) pavement tank hardstand, the first of its kind in Europe, was built for the U. S. Army at Harvey Barracks in...

Evaluation of Reservoir Seepage in Karst Topography
Areas where seepage is likely to occur in the karst environment of the proposed West County Reservoir, Roanoke County, Virginia have been indentified. Solutioning exists in the form of...

Exploring Karst Terrain with Air Track Drilling
Pneumatic-powered track-mounted, percussion drills can be used to perform or augment geotechnical investigations in some karst settings. The air track drill is best suited to exploring...

Regulatory and Environmental Issues of the Chisman Creek Superfund Site
This paper discusses the regulatory and environmental issues arising from the response to the Record of Decision (ROD) for the Chisman Creek Superfund Site in York County, Virginia. Field...

Evaluation of Air Quality Methods in the Asbestos Work Area
Air monitoring is a technique that is routinely used to measure the level of asbestos in a given airspace. This technique has changed significantly since its first use in the asbestos...

First-Order Reliability Analysis of Groundwater Flow
A method for stochastic analysis of groundwater flow based on the first-order reliability approach is presented. The method is well suited for problems in which statistical information...

Extent of Water Quality Effects of Dams?A National Viewpoint
An overview of phosphorus impacts on impoundments, a subset of the contents of the Dam Water Quality Report is presented. The U.S. Environmental Protection Agency (EPA) is the lead investigator...

A Simple Nonpoint Source Groundwater Quality Management Model
A model is examined which efficiently produces information required by decision makers to assess water quality tradeoffs associated with alternative groundwater protection strategies,...

Assessing WQ Impacts Using a Hydraulic Model
Engineering projects may cause water quality impacts in estuarine systems. It is important to assess those impacts during the planning phase of the project so that mitigation measures...

Modeling Water Supply Benefits of a Shallow Lake in a River Reach
Minimum flow and level requirements based on ecological, water quality, recreation and other needs are established and used as limiting criteria in the development of a riverine lake as...

 

 

 

 