Learning from Failures
Modern technology and innovation have created a gap between what the design drawings predict with respect to safety and serviceability of a structure and the real safety and serviceability...
Learning from Failures: Procedural Changes in the Design and Construction Process to Reduce Failures
This paper first defines failures and their number and scope in the design and construction fields. It then presents the writer's opinion as to the cause of the failures and...
Failure Investigations in Undergraduate Education
Author stresses the need for failure investigations in undergraduate education especially in Civil Engineering. The civil engineer often creates only one major project of a kind, and is...
The Consulting Engineer's Resident Engineer on Public Works Projects
The importance to the owner, engineering firm, and construction contractor of a qualified Resident Engineer on a construction project cannot be overly emphasized. Similarly, the duties,...
Project Coordination Resident Engineering Costs Versus Construction Costs for New York City Department of Environmental Protection
The paper explains how the New York City Department of Environmental Protection has successfully completed a 1 billion construction program using only resident engineer inspection services....
Project Administration
The paper discusses the vital issues involved for the efficient administration of a construction contract: effective communication, field office staffing, long lead procurement of equipment,...
Ensuring Quality Construction
This paper describes the US Army Corps of Engineers' efforts at procuring quality construction: 1) a three-phase approach (preparatory, initial, follow-up) was developed to...
Navy Construction Contract Administration
A U. S. Navy Civil Engineer Corps Officer portrays the varied responsibilities of a Resident Engineer administering construction contracts for the military service. The challenges, rewards...
The Corps Resident Engineer
The paper briefly defines the authority, duties and responsibilities of a resident engineer (RE) in the U. S. Army Corps of Engineers. Based on these, it is concluded that the RE has the...
Development of a Resident Engineer
The author discusses a development program suitable for a Resident Engineer to take up. Included in the requirements of the program are actual experiences, training courses and personal...
Cost Engineering for Disputed Work
Engineers and architects tend to underestimate the cost of disputed work, especially those connected with delay. The engineer, using industry standards and estimating rules of thumb, can...
Type C Fly Ash and Clay Stabilization
Because the soils onsite have a high swell potential, a 37 foot high retaining wall was designed with counterforts and was supported by pier foundations to limestone. In order to reduce...
Soft Ground Tunneling of the Greenbelt Tunnels
Mergentime/Loram's contract for the construction of Section E-1d Greenbelt Route Tunnels includes construction of dual 1,770-foot tunnels in soft ground, a crossover structure,...
Construction Inspection?The Last Line of Defense
Construction inspection, or a quality assurance program, is typically the last line of defense in relation to claims for the constructed project. The quality assurance team should be a...
A Systematic Approach to Evaluating the Risk of Contractual Disputes
Construction contract disputes along with A/E malpractice actions have raised much concern in the industry. Considerable literature has been written along the lines of claims avoidance...
Building Condition Assessment�An Owner's Perspective
The Port Authority of New York and New Jersey has recently instituted a program to inspect all of its buildings structures to insure structural integrity and public safety and to provide...
Evaluation and Modernization of Veterans Administration Facilitaties
This paper discusses two examples showing in detail that procedures for building assessment require much consideration for engineers' programming and must be properly specified...
Changing Priorities in UK Construction Research
This paper addresses two types of situations to contend with in building assessment: aging structures all built at about the same time and to standards no longer acceptable, and newer...
Research Needs for Extant Iron and Steel Buildings
A brief review of iron- and steel-making processes is background for the development of shapes and codes. Sources of information for the condition assessment of iron and steel buildings...
Structural Integrity Assessment of the Flexible 870 Advanced Design Bus
The Grumman Flxible 870, a lightweight advanced design urban bus, entered service in Atlanta, GA in 1978, and some 2,800 of these buses were in service nationwide by 1980. In the autumn...