Soft Ground Tunneling of the Greenbelt Tunnels
by J. Marshall Dean, Mergentime Corp, Flemington, NJ, USA,Document Type: Proceeding Paper
Part of: Tunneling Operations and Equipment
Abstract:
Mergentime/Loram's contract for the construction of Section E-1d Greenbelt Route Tunnels includes construction of dual 1,770-foot tunnels in soft ground, a crossover structure, a fan structure and pumping station, and other related work. This presentation describes the overall construction requirements of the Contract, including subsurface conditions; Mergentime's value engineering of the tunneling and compressed air contract requirement; selection of the tunnel boring machine; installation and use of the compressed air plant including the man, muck and medical locks; the use of precast concrete tunnel liners; and the tunneling performances during construction of the tunnels.
Subject Headings: Tunnels | Soft soils | Value engineering | Precast concrete | Construction equipment | Tunneling | Concrete construction
Services: Buy this book/Buy this article
Return to search