Hydraulic Model Studies - Sidney A. Murray Jr., Hydroelectric Plant
The power plant is located at the Old River Control of the Lower Mississippi River (Louisiana). It consists of an intake channel about 5000 ft long, a power plant with eight bulb units...
Physical Model Study of New York State Dam
The New York State Dam is located on the Mohawk River near its confluence with the Hudson River. Downstream from the dam, the river flow is divided into six channels as the water passes...
Moose River Air Chamber Design and Performance
The Moose River Hydroelectric Project is a 12.5 MW development located in upstate New York. It employs an underground air chamber to protect the unit and power tunnel from pressure surges...
Hydraulic Model Tests of Flow around Penstock Suspended inside the Tunnel for Design of a Small Hydro
The proposed hydropower project in the State of Virginia involves design and construction of a steel penstock hung from the crown of an existing outlet tunnel at this U.S. Army Corps of...
Safety Evaluation of PG&E Dams
Pacific Gas and Electric Co. (PG&E) owns and operates 71 hydroelectric power projects in Northern and Central California. With 115 dams in its system, PG&E is the largest...
Mitigation of Ice Effects at Hydroelectric Intake Structures
The design and operation of hydroelectric facilities throughout the northeast United States and Canada must contend with winter conditions for a large part of their yearly operation. During...
Relicensing: The New Rules of the Game
The Electric Consumer Protection Act of 1986 is an elaborate array of procedures and decisional standards that guide the Commission's consideration of both initial license and Federal...
Compliance Administration in the Office of Hydropower Licensing
Since the passage of the Electric Consumers Protection Act (ECPA) on October 16, 1986, the Commission has effected a number of organizational, programmatic and regulatory changes consistent...
Public Safety through Cooperation
This paper describes the present FERC dam safety compliance program. The program's philosophy and history, organization, and key elements as well as accomplishments are presented...
Licensing the Moose River Hydroelectric Project
This paper describes environmental considerations in the licensing and permitting of the Moose River Hydroelectric Project, a 12.2 MW development in Central New York State. It illustrates...
Effects of the Environmental Approval Process on Project Scheduling and Economics
The environmental approval process is fundamental to the permitting of hydropower projects. Recent changes in permitting requirements has had a significant effect on the cost and schedule...
Negotiating with State and Federal Fish and Wildlife Agencies
The Federal Power Act of 1920 (Act), as amended by the Electric Consumers Protection Act of 1986, requires that the Federal Energy Regulatory Commission, in order to adequately and equitably...
Licensing in the 1990's: Can FERC Be a One-Stop Shop?
The Federal Water Power Act of 1920 was enacted in order to create a comprehensive licensing scheme for hydroelectric power development. Central to that scheme was the consolidation of...
FERC's Experience in Analyzing Cumulative Impacts
Since the mid-1980's, the Federal Energy Regulatory Commission (Commission) has assessed cumulative impacts associated with developing proposed hydropower projects. A brief...
This article discusses recent developments in enforcement by the Federal Energy Regulatory Commission ('Commission' or 'FERC') of its...
Extensive Civil Penalities Apply - FERC Takes Aim at Hydro Operators' Heads
On August 23, 1988, the FERC published rules implementing its new civil penalty assessment authority. Those rules raise various issues of concern for hydro operators, and additional issues...
Optimum Use of the Water Resource a Factor in the Hydroelectric Relicense Process
To meet Federal Energy Regulatory Commission (FERC) requirements for a new license, owners must demonstrate full development of the available water resource. This paper presents an approach...
New Clues to PMP
Great changes have occurred in meterology in the last two decades. Formerly, weather data were available for forecasting and climatological analyses only at points - at weather stations....
Managing the Columbia River to Meet Anadromous Fish Requirements
According to northwest fishery agencies and Indian tribes the protection for juvenile salmon and steelhead is not adequate. The Northwest Power Planning Council, formed as the result of...
Radio Telemetry as a Tool for Fisheries Mitigation
Monitoring discrete fixed locations requires automated receivers and data loggers while manned, mobile receivers are more suited to general movement or habitat studies. Of the three tagging...
Return to search