Shafts/Temporary Structures
Shafts should be of a size to accommodate the equipment and pipe selected and to allow for safe working practices. If the shaft must accommodate the permanent works, it is the contractor's...
Construction Support Services
A preconstruction survey of existing structures within the anticipated construction zone of influence should be conducted before any construction begins. A plan for structures that need...
Regulations
The contractor should meet federal, state, and local regulations. The contractor is responsible for jobsite safety....
Instrumentation and Monitoring
A detailed plan for monitoring possible ground surface movements caused by the microtunneling operations should be prepared. The plan is typically prepared by the engineer in consultation...
Restoration and Cleanup
The contractor should be responsible for site restoration and keeping the construction site clean, neat, and orderly at all times....
Measurement and Payment
The owner shall establish a bid schedule to obtain pricing for all work associated with the microtunneling installation. This bid schedule provides the bidders the opportunity to establish...
Filling The Bay: Deepening the Oakland Inner and Outer Harbors
The project to deepen the Oakland Inner and Outer Harbors from elevation -42 to -50 ft was federally authorized in 1999 to accommodate the next generation of post-Panamax container ships....
Innovative Use of a Groin Structure: Saving Cost, Shortening the Schedule, and Minimizing Impacts
Almost any type of construction activity can pose a shock to the surrounding environment and habitat. Obviously, the extent of the impact will depend on the location of the project and...
The New Bedford Marine Commerce Terminal
When construction of the first American offshore wind farm support terminal encountered greater challenges than expected, jet grouting enabled construction to continue....
Findings From a Joint Industry Study on Foundation Fixity of Jackup Units
During the design storm conditions the soil supporting jack-up unit footings may be close to, or at plastic failure. Accordingly, the use of elastic solutions to the problems of foundation...
Geo-Congress 2014
Technical Papers and Keynote Lectures
Proceedings of the 2014 Geo-Congress, held in Atlanta, Georgia, February 23-26, 2014. Sponsored by the Geo-Institute of ASCE. GSP 234, Geo-Congress...
Failure of a Large Circular Excavation
A circular excavation, 117 feet (36 m) in diameter by 90 feet (27 m) deep, was designed by an experienced engineering firm and construction was performed by an experienced contractor....
Failure of a Twenty-Foot High Retaining Wall
A cantilever retaining wall, designed in apparent accord with provisions in a civil engineering handbook, failed soon after construction. Analyses of the causes of the failure are presented....
Advanced Fracture Control Procedures for Deepwater Platforms and Compliant Towers
This paper describes an integrated approach to fracture control problems � applied first as a necessary adjunct to the authors' own engineering practice, then in developing...
Case Study of Offshore Pile System Reliability
This paper presents the results of research effort to evaluate the reliability of offshore pile foundation systems. It is an extension of previous work by the authors [14] dealing with...
Sustainable Development � A Geotechnical Perspective
Sustainability has become a key factor in major construction projects these days, and many geotechnical engineers have started focusing on the concept. Owners, public agencies, and the...
Asset Management of Earth Retaining Structures: Design through Design Life
Regarding new earth retaining structures (ERS) construction, the message is clear: plan for asset management. New construction is certainly not immune to performance issues, and the time...
So, Why Do You Want to Write a GBR?
Since 1974, scores of papers, articles, conferences, and legal documents have been dedicated to explaining how to write and/or how to use a Geotechnical Baseline Report (GBR). But the...
Geo-Hubei 2014 244-255
Sustainable Civil Infrastructure, Innovative Technologies and Materials
Selected papers from the proceedings of the Geo-Hubei 2014 International Conference on Sustainable Civil Infrastructure, held in Yichang, Hubei, China, July 20-22, 2014. Sponsored by the...
Challenges and Risks of Jet Grouting in a Congested Urban Environment
In the heart of London, one of Europe's largest jet grouting contracts is nearing completion. The jet grouting is part of the overall 7-year-long upgrade project to London...