Uprating Francis Turbines Provides Additional Energy
The use of existing powerhouse, penstocks, dams and unit configuration, all provide for a quick cost effective method to increase output from an existing turbine installation. This paper...

Uprating Hydro Turbines and Generators
Various engineering evaluations of the turbine and generator components are required when considering uprating units. Often, certain turbine and generator components have to be redesigned...

The Lowell Hydroelectric Project: A Case Study
The Lowell Hydroelectric Project, located on the Merrimack River in Lowell, Massachusetts, consists of an existing dam, canals, and turbine generating equipment presently operating at...

Galt Energy's Inverted Siphon System
Galt Energy Systems' involvement with attempting to standardize the civil component began with studies at small remote sites in Northern Ontario. The system design evolved...

A New Generation of Standard Francis Spiral Turbines
A new generation of standardized Francis spiral case turbines has been developed by Voith. The high performance has been achieved through employment of the most recent hydraulic designs...

Hydroelectric Project Design Using Microcomputers
The main issue in the first stage of a hydroelectric project is to assess the influence of hydrologic parameters on design and optimum sizing of the installation and on future energy production....

Microcomputers as Productivity Aids for Small-Scale Hydroelectric Projects
Off-the-shelf software that has been used to improve productivity includes Computer-Aided-Design-and-Drafting (CADD) systems, spreadsheets, project managers, word processors, and communications...

Seismic Isolation System for a Floating Dry Dock
The seismic isolation system consists of two dolphins, each a relatively large-diameter cantilevered steel pipe pile anchored in Franciscan rock, and buffered connections to the floating...

LRFD Format for Transmission Structures
The structural design of high voltage electric transmission lines in the US is usually governed by the National Electrical Safety Code (NESC). A simple reliability-based Load and Resistance...

A Field Study of Wind-Induced Conductor Loads
A 161 kV steel pole line in Omaha, Nebraska, is instrumented to provide conductor load field data due to climatic events. Various transducers and monitoring equipment used for data acquisition...

Lattice Tower Design Using Cold-Formed Shapes
The use of cold-formed shapes in lieu of hot-rolled angles may lead to major changes in the design of lattice transmission towers. The design procedure of the new shapes is more creative,...

Cold-Formed Angles for Transmission Towers
Cold-formed members enable the engineer to design transmission towers that may be more cost-effective than those built with hot-rolled angles. Members can be designed to closely fit the...

Design and Test of Cold Formed Steel Members
Latticed systems represent the most spread and low-cost solution for electrical trasmission towers, when ground conditions do not affect the design choice. Steel angles have been used...

Bolted Connections for Steel Towers
Laced electrical transmission towers require on-site assembly. Consequently, the number of bolts and pieces are important considerations in the total cost of the structures. ASTM A394(1)...

Design of Drilled Piers Subjected to High Overturning Moments
The results are presented of a research study directed at improving the state-of-practice, and resulting foundation economy, in the design of laterally loaded drilled pier foundations...

IEEE/ASCE TransmissionStructure Foundation Design Guide
The American Society of Civil Engineers' (ASCE) Subcommittee on Foundation Design for High-Voltage Transmission Structures was formed in October 1976. The purpose of the Subcommittee...

Strength Data Base for LRFD of Transmission Lines
Reliability-Based Load and Resistance Factor Design (LRFD) has been proposed as a desirable alternative or a complement to the National Electrical Safety Code (NESC) for the structural...

Special Pile Foundations for a Coastal Permafrost Site
The design of the plant's foundations had to address several challenging geotechnical conditions. These included (1) 'warm' (close to 32 degree F)...

Design of Tension Member Insulated Anchor for Arctic Pipelines
This paper explores the latest development in above-ground waterflood pipe anchors currently being used on the SOHIO operated portion of the Prudhoe Bay Oil Field. The objective of the...

Costs of Truck Related Highway Damage to Alaska
The cost of pavement damage to the State of Alaska for truck traffic continues to be a very controversial topic. There is no simple answer since this cost is dependent upon pavement strength,...

 

 

 

 