Appropriate Design and Construction of Conduits for Small and Mini Hydropower
The success of smaller hydro schemes often lies in identifying feasible and economic waterway systems to develop relatively high heads between low intake weir and powerstation. This paper...

Early Detection of Rotor Cracks?Monitoring & Methodology
This paper describes a diagnostic method for the early detection of shaft cracks on rotating machines. The method is based on interpretation of the lateral synchronous (1x) and twice per...

Osoyoos Lake Control Structure
The new Osoyoos Lake Control Structure has been built on the Okanogan River at Oroville, Wa. The site is about 2 miles downstream from the outlet of Osoyoos Lake, and about 9 miles south...

Variable Speed Generators in Hydro Applications
This paper discusses the investigation of the doubly-fed variable speed machine as a potential candidate to convert a varying input speed to a constant frequency, constant voltage output....

Characteristics of the Roesel Machine Used for Small Scale Hydro/Wind or Sea Wave Electric Power Generation and Storage
An electrical machine with property of synchronous as well as asynchronous characteristics and based on ceramic magnet programming technology by continuous printing of the desired number...

Analysis of Hydraulic Transients for Design and Operation of Two Powerhouses in Series
The Dinkey Creek Project will be located in the southern Sierra Nevada mountains 40 miles north-east of Fresno, California, and will develop about 4000 ft of gross head with a maximum...

Free-Rotor, River-Velocity Turbine
This paper discusses the development of a very simple and inexpensive underwater turbine which will extract power ranging from a fraction of a HP up to 20 HP from the velocity of the running...

Turbine Casing and Distributor Hydraulic Design
Interactive casing and distributor hydraulic design and flow analysis software has been developed and tested. Until now, its application is limited to radial distributor turbo-machines....

Bureau of Reclamation Uprating Program
The Bureau of Reclamation is an agency of the Department of the Interior and was established in 1902 to oversee the development and conservation of the Nation's water resources...

Field Observations of Cavitation Erosion in Hydraulic Turbines
Field surveys of the operational and design characteristics of 602 hydroturbines installed since 1950 and having a capacity in excess of 20 MW or a discharge diameter greater than 3 meters...

Fire Protection at the Grand Coulee Hydro Project
In the fall of 1980 a rupture of one of the Project's 525kV transmission cables occurred and created a fire. Power from three Third Powerplant 700MW units was interrupted,...

Index Testing With a Data Acquisition and Control System
A computer controlled index test has been developed that can be used to optimize blade-gate relationships on adjustable blade (Kaplan) hydraulic turbines. This paper includes hardware...

Design and Commissioning of the Philadelphia Hydroelectric Project
The Philadelphia Hydroelectric Project consists of a single horizontal-shaft double-regulated S-type unit, rated 3440 kW, utilizing a programmable controller for unit operation together...

Digital Control of 180MW Francis Turbines: Controller Design, Simulation, and Operational Results
The features of a new hydro-power station are outlined as are some specifications that the customer required of a digital controller. Both hardware and software aspects of this recently...

Programmable mMicroprocessors in Local Control of Hydro Power Plants
The main purpose of the control equipment is to provide the generator with means for operation of the power station equipment. There is a need for status information on the generating...

An Integrated Site Controller-Network Monitoring System for Small Scale Hydroelectric Sites
Over the past decade more and more small scale hydroelectric power developers have faced the question of the economic feasibility of installing microprocessor based control systems for...

Efficiency in Auxiliary Electrical Systems
In 1984, during the preliminary design for the proposed second powerhouse at the Corps of Engineers' McNary Dam on the Columbia River, the more recent improvements and techniques...

Grand Coulee SCADA System Procurement
Purchasing a quality Supervisory Control and Data Acquisition (SCADA) or Energy Control System (ECS) at a reasonable price for a particular installation can be a challenging undertaking....

Generator/Motors and Adjustable-Speed Drives for Waddell Pumped-Storage Plant
This paper describes the pumping and generating units and associated electrical equipment planned for Waddell Pumped-Storage Plant. Waddell Pumped-Storage Plant is to be located near Phoenix,...

Kaplan Blade Angle Controller
This paper describes a recently developed computerized Kaplan blade angle controller that is capable of improving turbine performance. Model Tests or Index Tests produce the Three-D-Cam...

 

 

 

 