Khao Laem?A Concrete Face Rockfill Dam on Karst
A continuously reinforced concrete faced rockfill dam has been successfully designed and constructed on a karstic limestone foundation in Central West Thailand. The dam is not in an earthquake...
Kotmale Dam and Observations on CFRD
A concrete faced rockfill dam was the type selected for the 300 ft (90 m) dam at Kotmale in Sri Lanka for reasons of economy and speed in construction. Standard design concepts were tailored...
Design of Concrete-Faced Rockfill Dams
Design principles adopted in 1966 by the Hydro-Electric Commission have been applied to nine concrete-faced rockfill dams and remain substantially unchanged. Experience shows that the...
Design of Deer Creek Dam
The Deer Creek Dam is proposed to be a concrete face rockfill structure (CFRD) with upstream and downstream slopes nominally 1. 3 horizontal to 1 vertical. The embankment will rise 280...
Machadinho Dam in Brazil
This paper presents the reasons for selection of a concrete-face rockfill dam for Machadinho Hydroelectric Project in Brazil. It also describes the main characteristics of the dam, as...
The Design of Macagua Concrete Face Rockfill Dam
This article describes the design characteristics of the concrete face rockfill dam at Macagua, which will have a total length of about 9,200 ft (2,800 m), an average height of 66 ft (20,0...
Foundation Design Considerations for Detroit DPM
The design loadings for support of the elevated guideway of the Detroit Downtown People Mover (DPM) consist of high vertical as well as horizontal loads. In order to simplify foundation...
Design of Cirata Concrete Face Rockfill Dam
The Cirata Hydro-Electric Project on the Citarum River in Western Java, Indonesia is at present under construction for Perusahaan Umum Listrik Negara (PLN). The project which is being...
Applications of Microcomputers for Bridge Design
This paper examines the role of microcomputers in the design divisions of state departments of transportation, specifically in bridge design applications. Consideration is given primarily...
Vibration Problems in Geotechnical Engineering
This volume constitutes the Proceedings of a two-session Symposium whose main objective is to address geotechnical issues related to vibration problems other than those associated with...
Uplift Behavior of Anchor Foundations in Soil
This publication includes a series of studies which provide a general and consistent framework for the design of anchors in uplift. The papers are presented in three groups: (1) State-of-the-art...
Concrete Face Rockfill Dams?Design, Construction, and Performance
Concrete face rockfill dams are being used with greater frequency and to greater heights in the last decade. The developments leading to this progress are many and are addressed in the...
Structural Design, Cementitious Products, and Case Histories
The papers in this book represent deverse topics in structural engineering. In design of beam-columns by the AISC interaction equations, it is demonstrated that an inadequacy exists when...
Current Research and Research Needs in Deep Foundations
This report summarizes the current range of research on deep foundations now being performed in the United States. The report is divided into two main sections: (1) Current research or...
Tunneling a Bridge
Linking an addition to the Georgia World Congress Center in Atlanta required a pedestrian tunnel through a railroad embankment 100 ft wide and 40 ft high, with no disruption of train service...
Advances in Short Span Steel Bridges
Applying recent research to the design of short span steel bridges can lower their cost and maintenance. Such research involves improved limit state criteria, more uniform lateral load...
Jointless Bridge Decks
Deck joints in a bridge are the source of many problems over its lifetime. In time, chances are good the joint will leak, permitting water and salt to leak through. Often this leads to...
USBR Design Considerations for Roller Compacted Concrete Dams
Current Bureau design criteria for concrete dams are based on analytical methods developed and improved over the years, evaluation of construction methods and post construction materials...
Redecking with Precast Keeps Traffic Moving
The Woodrow Wilson Memorial Bridge in Washington, D.C. could not be closed to traffic while a new deck was constructed. The engineers designed a precast prestressed and post-tensioned...
Rail and Road Traffic Continue During Bridge Modification
The crossing of Route 15 under the Bangor and Aroostook Railroad Bridge, Bangor, Maine had limited sight distance and marginal clearances. Maine Department of Transportation, therefore,...