A Case for Selecting Only Deterministic Spillway Design Floods for High Hazard Dams
The Federal Energy Regulatory Commission has under license or exemption from licensing more than 2000 hydroelectric dams. The Office of Hydropower Licensing published, in September 1986,...
Repair of The Hinckley Dam Embankments
The New York Power Authority was licensed in 1982 to construct and operate a 9 Mw hydroelectric facility at the existing Hinckley Dam near Utica, New York. Soil exploration programs undertaken...
Roller-Compacted Concrete for Dams
This paper summarizes the findings of an investigative report on roller-compacted concrete dams prepared by Morrison-Knudsen Engineers, Inc. (MKE) under contract to the Electric Power...
Cedar Falls Project-Rehabilitation with RCC
This paper presents an overview of the planning, design, and construction considerations used during the development of the 9. 1 m (30-foot-high) Cedar Falls Roller Compacted Concrete...
Dam Safety Emergency Action Plans?A TVA-State Responsibility
The Federal Guidelines for Dam Safety requires each dam owner to prepare and maintain emergency action plans (EAP) for each of structure. These plans are necessary (1) to identify problems...
Designing a Modern Small-Scale Hydroelectric Plant
STS Consultants, Ltd. (STS) and Skidmore, Owings & Merrill (SOM) successfully teamed on four hydropower sites in Michigan during the 1980's. Three of the four sites...
Milltown Powerhouse Rehabilitation
The Milltown Powerhouse and dam are over 80 years old. The powerhouse and other structures were built in 1906 and are owned by the Montana Power Company. The plant is located on the Clark...
Modern Technology in an Ancient Environment?The Answan II Power Plant
The Aswan II power plant is located at the old Low Aswan Dam in Southern Egypt. This dam was constructed in the early years of the century in order to provide irrigation water for cash...
New Martinsville Hydroelectric Project
The 34MW New Martinsville Hydroelectric Project is presently under construction in West Virginia. Located at Hannibal Locks and Dam near river mile 126 downstream from Pittsburgh, PA,...
Large Capacity Rock Anchors Stabilize Bagnell Dam
Evaluations of spillway discharge capacity and stability of structures for the Osage Hydroelectric Project indicated that the Project was unsafe during the occurrence of the Probable Maximum...
The Rehabilitation of Lake Harriet Dam
In 1984, the decision was made to rehabilitate the Lake Harriet Dam. The existing arch dam structure was encased with a rockfill buttress. The downstream buttress, which also acts as a...
Cedar Falls Project?Major Rehabilitation
This paper presents planning objectives and operational considerations which governed the design and construction of a major rehabilitation project implemented at the City of Seattle's...
Green Mountain Power Corporation Bolton Falls Hydroelectric Project
The project proceeded through preliminary design, FERC licensing, and into detailed design, following its selection as one of seven low-head redevelopment projects to be partially funded...
Hydro Combine Option for Lakhwar Project
A new concept of providing a power house cavity inside the traditional gravity dam section has been explored. Preliminary investigations indicate that taking into account all the relevant...
Single Conduit Dam Design
In today's arena of increasingly higher costs for major dams, planners and designers are continuing to look into ways of reducing the overall costs for the development of...
Waterstop Technology?The Next Chapter
Water leakage through and around failed waterstops in concrete structures can cause serious flooding, damage to equipment, affect structural stability, and pose potential safety problems....
The Use of Polyurethane Grouts and Grout Tubes
Most polyurethane grouts used for seepage control are one-component, and water activated. They are prepolymers of a polyisocyanate with a polyol. Some of the polyurethane grouts use an...
OK Menga Hydroelectric Project, Papua New Guinea
The Ok Menga project, currently under construction, consists of a run-of-river intake underground concrete and steel lined power conduit surface powerhouse with two 25 MW units and a 132...
The Effect of Geology on the Dinkey Creek Project
The proposed Dinkey Creek Project is located about 40 miles northeast of Fresno, California. The project consists of a 360-foot high rockfill dam, two powerhouses, 41,600 feet of power...
Geotechnical Exploration?Rio Bravo Hydro Project
In order for the Rio Bravo Hydroelectric Project to become a reality, a thorough evaluation of alternative project configurations was necessary. Various power canal shapes, sizes, and...
Return to search