A Coastal Hard Rock Sediment Budget for the Inner Bristol Channel
The dominant input into the inter-tidal zone from the hard rocks bordering the inner Bristol Channel is clastic material. This is derived from coastal recession as a result of subaerial...

Uplift under Concrete Dams on Rock
While the possible existence of uplift pressures within dams and foundations is no longer questioned, there is still considerable controversy over the magnitude and distribution of uplift...

Uplift Pressure below Gravity Dams on Rock
The magnitude of the uplift force at the base of a concrete gravity dam founded on rock is strongly dependent on the properties of the discontinuities within the rock mass. This paper...

Lopez-Angostura Power Tunnel
The Lopez-Angostura Project is located on the Yaque del Norte River in the Dominican Republic near the City of Santiago. A 24 m high dam, a 3.6 km long power tunnel, a pit powerhouse with...

Design Considerations for a Penstock Located in an Outlet Tunnel at the Jennings Randolph Dam in West Virginia
The proposed production of hydropower at this flood control-recreation dam involves the installation of a 78 inch diameter steel penstock at the crown of the existing tunnel. The penstock...

Dam Rehabilitation and Fish Lift Design at the Pejepscot Hydroelectric Project
The rehabilitation work on the existing rockfilled timber crib dam comprised an assessment of the existing dam stability; analysis of the existing hydraulic conditions to establish the...

An Evaluation of the Applicability and Cost of Polyester Resin and Cementitious Grouts for the Installation of Rock Anchors at Hydro Projects
The success of two proposed hydropower projects in the States of Virginia, and West Virginia depended on the ability of a rock anchor system to support the penstocks at the crown of the...

Visual Scheduling
This paper presents a look at new innovative way to provide project schedule. The primary target is in visual scheduling presentation techniques. The systems presented include a system...

Large Capacity Rock Anchors Stabilize Bagnell Dam
Evaluations of spillway discharge capacity and stability of structures for the Osage Hydroelectric Project indicated that the Project was unsafe during the occurrence of the Probable Maximum...

The Rehabilitation of Lake Harriet Dam
In 1984, the decision was made to rehabilitate the Lake Harriet Dam. The existing arch dam structure was encased with a rockfill buttress. The downstream buttress, which also acts as a...

Civil Design of Underground Hydro Power Projects
Various reasons exist for the development of underground schemes. Limited space at dam sites in deep and narrow river valleys makes it favourable to separate the power house from the dam...

Rock Engineering at Cat Arm Hydroelectric Development
Cat Arm Hydroelectric Development in Newfoundland, Canada, develops 129 MW from 384 m of head. The project was constructed between 1981 and 1984 and comprises 5 large dams, 5 small dams,...

The Effect of Geology on the Dinkey Creek Project
The proposed Dinkey Creek Project is located about 40 miles northeast of Fresno, California. The project consists of a 360-foot high rockfill dam, two powerhouses, 41,600 feet of power...

Adapting Tunneling to Rocks of the Sierra Nevada
Exploration programs were completed to select the most economical tunnel routes which are not only the shortest but are those which can be excavated by tunnel boring machines with the...

Lake Tap?Crater Lake
The Crater Lake Phase of the Snettisham Hydroelectric Project has been designed and is currently under construction. This paper describes the design and construction of the lake tap which...

High Pressure Grouting of the Bath County Tunnel System
A major grouting program was completed at the Bath County Pumped Storage Project between March and September 1985. High pressure grouting for seepage reduction was completed in a total...

Subsurface Savings
Less conservatism than usual in designing building foundations is being accepted or demanded by some owners to save money. The article describes four examples of cost-cutting innovations,...

The MPSP System: A New Method of Grouting Difficult Rock Formations
In unstable rock masses the traditional stage grouting methods may prove impractical or ineffective. A recent innovation has been the Multiple Packer Sleeved Pipe (MPSP) System. Akin to...

Highway Damage Due to Subsidence
In this study subsidence profiles over three longwall panels, which were mined beneath state highways in Southeastern Ohio, were obtained. Immediate and short term subsidences were recorded....

Rock Armouring to Unconventional Breakwaters: The Design Implications for Rock Durability
This paper identifies the need for quantitative durability testing of rock for use on dynamically stable rock armored slopes. The derivation and use of a suite of engineering tests for...

 

 

 

 