Quick Checks for Structural Computer Analysis
When working with general structural analysis programs, there are some fast ways to check the input and output. This paper reviews some methods for verification of results of computerized...

Facilitate Delay Claim Analysis with As-Built Schedule Databases
A computer-based As-Built Schedule Database can provide a useful tool for the investigation of project performance. The facts recorded in the database may be used to identify actual sequential...

Computer Use in Claims Analysis -- Roundtable Discussion
Preparation or defense of construction claims is inherently time consuming and often counter-productive. This outline discusses some tools currently used in the construction industry to...

CadVisor (CAD Equipment Analysis and Selection System)
This paper describes a system called CadVisor (CAD Equipment Analysis and Selection System) developed by the U.S. Army Corps of Engineers Construction Engineering Research Laboratories...

Use and Abuse of Settlement Analysis
Terzaghi's concept of settlement analysis included comparison of prediction with reality and investigation of the causes of the differences. Present usage is often limited to prediction....

Settlement of Embankments on Soft Clays
It is now possible to make reliable predictions of settlement of embankments on soft clays. In most situations, where the embankment is designed to resist undrained instability during...

Settlement of Tanks on Clay
Steel tanks for storage of water, oil, and other liquids are capable of withstanding large, but not unlimited, settlements without damage. In most cases shallow foundations provide adequate...

Mat Foundation Design: An Historical Perspective
Nearly a half century ago, Karl Terzaghi rationalized the analysis and design of mat foundations with the conclusion that subgrade reaction was the most important variable. Soon after...

53 WAK Tests on Spread Footings
Research on the prediction of soil stiffnesses of spread footing-soil systems using Wave Activated Stiffness (K) or WAK tests was conducted. As discrete lumped-parameter model with a mass,...

Vertical and Horizontal Deformations for Foundations on Sand: An Experimental Study
A natural scale model is used in order to investigate experimentally the sand soil deformation behavior which accepts loads by shallow foundations. The vertical and horizontal soil displacements...

Settlement Behavior of an Avalanche Protection Gallery Founded on Loose Sandy Silt
An avalanche protection gallery located in the Swiss Alps was founded on alluvial ground close to the steep rocky mountainside. The rear retaining wall, at a variable distance of a few...

Displacement of Landmark Building Resulting from Adjacent Construction Activities
This paper describes the observations and presents comments related to the measurement of settlement and the avoidance of damage to a historic structure in the City of New York from adjacent...

Horizontal and Vertical Movements of Bridge Piers Subjected to Ship Impact
Results of a detailed analysis to evaluate the potential horizontal and vertical movements of the piers of George P. Coleman Bridge, Virginia, in the event of ship impact are presented...

Static Pile Load-Movement From Dynamic Measurements
Static loading tests have traditionally been performed to determine the characteristics of pile load-movement relationships. Due to the expense involved and time required, this type of...

Numerical Study of Underpinning by Piles for Settlement Control of Strip Foundations
A numerical study has been carried out of a simple idealized problem of a shallow strip foundation (both flexible and rigid) on clay underpinned by rows of piles. The work is directed...

Design and Performance of a Piled Raft Foundation
The foundation system for a recently constructed building in Perth, Western Australia, consisted of combined pile groups and raft elements, with a total of 280 bored piles incorporated...

Wanapum Dam Embankment Settlement Study
This paper discusses the long term vertical movements of a zoned earth embankment. Vertical movement of the Wanapum Dam embankment has been monitored since its completion in 1964. The...

Analysis of the Juturnaiba Embankment Dam Built on an Organic Soft Clay
The Juturnaiba Dam, located in the northern part of Rio de Janeiro State, Brazil, has 1.2 km of its length built on an organic soft clay about four meters deep. The construction of the...

Settlement of a 15-Meter Deep Fill Below a Building
The site for a building in western Pennsylvania was undermined, with the mine base about 15 m below planned final grade. Rock above the mine was highly fractured and of poor quality, indicating...

Performance of Nanhua Dam During Construction
The pore pressure response and settlement during the construction of Nanhua dam were studied by several methods, including Hilf's method, laboratory stress path simulation and numerical...

 

 

 

 