Calibration of Jackup Leg Foundation Model Using Full-Scale Structural Measurements
The fitness of jack-up rigs to operate in varying water depths and weather conditions is determined by "site-specific" structural assessments. These assessments are conducted by a wide range of companies...

Design of Submarine Pipelines Against Upheaval Buckling
This paper describes part of a comprehensive joint-industry project on upheaval buckling. It develops a semi-empirical simplified design method and detailed design methods based on a new numerical analysis,...

Heave Compensated Landing System - A Novel Tool for Subsea Intervention
This paper presents a new intervention system that allows the use of a low cost workboat to deploy and recover delicate payloads in subsea installations. Vessel motions are decoupled from the subsea package...

Offshore Technology in Civil Engineering
Hall of Fame Papers: Volume 11
Prepared by the Program Committee of the Offshore Technology Conference of the Coasts, Oceans, Ports, and Rivers Institute of ASCE<\p>Offshore Technology...

Improving Cost and Schedule Performance on Municipal Pipeline Projects: Realizing the Benefits of the Construction Manager at Risk (CMAR) Alternative Project Delivery Method
The water and wastewater infrastructure in the United States is failing. In its 2013 Report Card on American Infrastructure, ASCE stated: "The water and wastewater...

Scope
This standard guideline covers planning, design, pipe materials, and construction of microtunneling. The term microtunneling is defined as a trenchless construction method for installing...

Project Layout
Microtunneling projects should be laid out with attention to the benefits and constraints unique to this construction process. The following recommendations address some of these concerns:...

Shaft Considerations
Jacking and receiving shaft locations should be selected to minimize the number of shafts and disruptions while not exceeding the practical limits of the drive lengths achievable for a...

Pipe Characteristics
Microtunneling pipe should meet the following general requirements: Circular shape with a flush outside surface (including at the joints); Strength sufficient to withstand both the installation...

Pipe Design
The pipes and joints, once installed, must be capable of safely withstanding, for the project design life, all in-use service loads, including those associated with the following factors:...

Field Aspects
As soon as practical after their arrival at the project site, all pipes, fittings, and appurtenances should be thoroughly checked for compliance with the contract documents and accepted...

Shafts/Temporary Structures
Shafts should be of a size to accommodate the equipment and pipe selected and to allow for safe working practices. If the shaft must accommodate the permanent works, it is the contractor's...

Innovative Use of a Groin Structure: Saving Cost, Shortening the Schedule, and Minimizing Impacts
Almost any type of construction activity can pose a shock to the surrounding environment and habitat. Obviously, the extent of the impact will depend on the location of the project and...

The New Bedford Marine Commerce Terminal
When construction of the first American offshore wind farm support terminal encountered greater challenges than expected, jet grouting enabled construction to continue....

Notes on Heavy Lift Design
The interrelated activities and responsibilities of the various organizations involved in the lift design and offshore installation of topside facilities for an offshore platform are discussed....

Performance Limits for Deepwater Pipelines
This paper highlights the differences between onshore and offshore pipeline design. It then summarizes the results of combined external pressure, tension, and bending testing on full scale...

The Joint Industry Development of a Recommended Practice for the Site Specific Assessment of Mobile Jackup Units
The mobile self-elevating (drilling) unit, or jack-up, has been central to the exploration and development of offshore oil and gas reserves. In recent years there has been an increased...

A Simple Model to Predict Soil Resistance to Driving for Long Piles in Deepwater Normally Consolidated Clays
As the exploration and development for offshore oil and gas reserves moves into the deepwater environment of the continental slope, a good model is necessary to evaluate drivability of...

Axial Load Capacity of Pipe Piles in Sands
The axial load capacity of driven, open-ended, steel pipe piles in cohesionless soils, is often estimated using a method such as the American Petroleum Institute Recommended Practice 2A...

Behaviour of Open-Ended Pipe Piles in Sand During Installation and Loading
An experimental study was performed to investigate the physical processes which influence the axial load capacities of open-ended steel pipe piles in sand. A double-walled pipe pile was...

 

 

 

 