New Exchequer Dam, California
New Exchequer Dam design, in 1963, was in the transition period in which dumped rockfill was being recognized as having undesirable settlement characteristics, and compaction of rockfill...

Weak Rock in Two Rockfill Dams
Two South Australian concrete face compacted rockfill dams, built from soft rock won from each dam site, have performed successfully in service with only small leakage and settlements...

Design and Performance of Shiroro Rockfill Dam
Shiroro Dam, constructed across the Kaduna River in Nigeria, is a rockfill dam with reinforced concrete facing. The dam was completed in late 1983, and reservoir impounding started in...

Design Features of Salvajina Dam
Salvajina dam is the second highest concrete face rockfill dam currently in service in the world. The characteristics of the foundation of the toe slab vary from fresh, sound and little...

Construction and Performance of Salvajina Dam
Salvajina Dam was constructed between July, 1982 and November, 1984. Relevant construction aspects are described, particularly those related with procedures and statistical data of the...

Khao Laem?A Concrete Face Rockfill Dam on Karst
A continuously reinforced concrete faced rockfill dam has been successfully designed and constructed on a karstic limestone foundation in Central West Thailand. The dam is not in an earthquake...

Kotmale Dam and Observations on CFRD
A concrete faced rockfill dam was the type selected for the 300 ft (90 m) dam at Kotmale in Sri Lanka for reasons of economy and speed in construction. Standard design concepts were tailored...

Design of Concrete-Faced Rockfill Dams
Design principles adopted in 1966 by the Hydro-Electric Commission have been applied to nine concrete-faced rockfill dams and remain substantially unchanged. Experience shows that the...

Design of Deer Creek Dam
The Deer Creek Dam is proposed to be a concrete face rockfill structure (CFRD) with upstream and downstream slopes nominally 1. 3 horizontal to 1 vertical. The embankment will rise 280...

Machadinho Dam in Brazil
This paper presents the reasons for selection of a concrete-face rockfill dam for Machadinho Hydroelectric Project in Brazil. It also describes the main characteristics of the dam, as...

The Design of Macagua Concrete Face Rockfill Dam
This article describes the design characteristics of the concrete face rockfill dam at Macagua, which will have a total length of about 9,200 ft (2,800 m), an average height of 66 ft (20,0...

Foundation Design Considerations for Detroit DPM
The design loadings for support of the elevated guideway of the Detroit Downtown People Mover (DPM) consist of high vertical as well as horizontal loads. In order to simplify foundation...

Design of Cirata Concrete Face Rockfill Dam
The Cirata Hydro-Electric Project on the Citarum River in Western Java, Indonesia is at present under construction for Perusahaan Umum Listrik Negara (PLN). The project which is being...

Vibration Problems in Geotechnical Engineering
This volume constitutes the Proceedings of a two-session Symposium whose main objective is to address geotechnical issues related to vibration problems other than those associated with...

Uplift Behavior of Anchor Foundations in Soil
This publication includes a series of studies which provide a general and consistent framework for the design of anchors in uplift. The papers are presented in three groups: (1) State-of-the-art...

Concrete Face Rockfill Dams?Design, Construction, and Performance
Concrete face rockfill dams are being used with greater frequency and to greater heights in the last decade. The developments leading to this progress are many and are addressed in the...

Structural Design, Cementitious Products, and Case Histories
The papers in this book represent deverse topics in structural engineering. In design of beam-columns by the AISC interaction equations, it is demonstrated that an inadequacy exists when...

Current Research and Research Needs in Deep Foundations
This report summarizes the current range of research on deep foundations now being performed in the United States. The report is divided into two main sections: (1) Current research or...

USBR Design Considerations for Roller Compacted Concrete Dams
Current Bureau design criteria for concrete dams are based on analytical methods developed and improved over the years, evaluation of construction methods and post construction materials...

LAX Takes Flight for the 1984 Olympics
LAX (the Los Angeles airport) had over two dozen contractors working on site to complete their $700 million improvement plan in time for the Olympics in July. They also came up with several...

 

 

 

 

Return to search