First 10 Years of Operation of The La Grande Hydroelectric Complex
The first turbine of the La Grande hydroelectric Complex (Quebec, Canada) was commissioned in october 1979. Since then, five reservoirs, two rivers diversions, three power stations with...

Sediment Evacuation System for Impounded Rivers
Current solution techniques for the reservoir sedimentation problem are presented and their rationale questioned. The need for focusing on the overall river transport regime is emphasized....

How Many Years to Fill with Sediment, a Sediment Study of Lake Powell on the Colorado River
A study to determine the current capacity and to update information on the life expectancy of Lake Powell was conducted by the Bureau of Reclamation. The study documented the present storage-elevation...

Automation of Existing Dam Control Schemes
For installations that are already in operation, the following advantages are obtained from installing new electronic equipment: In the case that the dam or certain measuring stations...

World Class Manufacturing and Hydro-Electric Production
Operations, maintenance, and administration and support services can benefit from the concepts of World Class Manufacturing. Cellular organizational concepts whether its machines, people,...

Underwater Tunnel Inspection by Virginia Power Using a Submersible Robot
The Bath County Pumped Storage Station, jointly owned by Virginia Power and Allegheny Power systems and operated by Virginia Power, has three large tunnels linking the upper and lower...

Tunnels and Vertical Shafts for Pumped-Storage
Economic considerations are of primary importance to the planning and designing of pumped-storage in an electrical generation and distribution system. This paper deals with the optimum...

The Modification of Leroy Anderson Dam
An extensive modification program has been implemented to improve the safety and enhance the performance of the Leroy Anderson Dam. The Leroy Anderson Reservoir has a maximum storage of...

Optimization of Power Production Based on Efficiency Data
Computer programs dealing with different parts of the optimization process are in operation in Norway today, and they include: the hydrological part from weather forecast to reservoir...

Evaluation of Hydro Facilities for Sale to Another Utility
STS Hydropower had been contacted by a major industrial client near one of the STS regional offices for the purpose of evaluating both the technical and financial status of several operating...

Turbine Runner Procurement for the Robert Moses Niagara Power Plant Upgrade
Procurement of the new runners involved the selection of two manufacturers who have entered into a design competition in which competing models will be tested in an independent hydraulic...

Development of High Specific Speed Pump-Turbines
The operational range of pump-turbines is continually increasing, especially in the direction of high specific speed installation. In this context, high specific speed refers to units...

Design and Installation Concepts for High Capacity Pump/Turbines
This paper discusses the pre-planned field welding and machining operations utilized for six (6) large pump/turbines, each capable of 508 MW at Virginia Power Company's Bath...

Field Efficiency Tests of a Large Pump-Turbine
The New York Power Authority's Blenheim-Gilboa Pumped Storage Project began commercial operation in 1973. In 1987, the Authority initiated a study of the existing pump/turbines...

Murray?Commissioning Maxi Hydro with Mini Flow
The Murray Hydroelectric Project contains two of the largest pit turbines in the world. An existing dam constructed for navigation and flood control on the Arkansas River, Lock and Dam...

320 KW Hydro Power Plant for Tenwek Hospital, Kenya, East Africa
Due to increasing demand for medical care and growth of hospital and staff facilities, a less costly source of electrical power was needed for the Tenwek hospital to replace the diesel...

Buffalo Bill Dam Modifications?Modification of an Existing Bureau of Reclamation Facility to Increase Power Generation
This paper describes a joint venture between the United States Bureau of Reclamation and the State of Wyoming to increase the storage capacity and power generation capacity of Buffalo...

Domed Renovations
Inside the granddaddy of domed stadiums, the Houston Astrodome, 10,000 new seats and 72 new suites were hung from a strengthened structure. Using a variety of working-with-what-we've-got...

Parking Garage Crisis
Corrosion in reinforced concrete parking garages is reaching crisis proportions. The rehabilitation market for these structures is estimated to be as much as $750 million a year, or 30%...

Reliability Analysis of Water Distribution Systems
Prepared by the Task Committee on Risk and Reliability Analysis of Water Distribution Systems of the Committee on Probabilistic Approaches to Hydraulics of the Hydraulics Division of ASCE....

 

 

 

 

Return to search