Integrated Test Evaluation Decision Framework for the Yucca Mountain Project
An Integrated Test Evaluation decision framework and computer model were developed to help prioritize site-characterization tests at Yucca Mountain. An initial application of the framework...

Software Quality Assurance on the Yucca Mountain Site Characterization Project
The Yucca Mountain Site Characterization Project (YMP) has been involved over the years in the continuing struggle with establishing acceptable Software Quality Assurance (SQA) requirements...

Qualification of Existing Data for the Yucca Mountain Site Characterization Project
The U.S. Department of Energy (DOE) has completed its first effort to qualify existing data using NUREG-1298 'Qualification of Existing Data for High-Level Nuclear Waste Repositories'....

Yucca Mountain Site Characterization Project Performance Based Q List
In mid-1992, the Yucca Mountain Site Characterization Project (YMP) initiated a performance based 'Q' List development effort. This effort is intended to evolve a 'Q' List based upon the...

A Variation of the Housing Unit Method for Estimating the Age and Gender Distribution of Small, Rural Areas: A Case Study of the Local Expert Procedure
This paper examines the suitability of a survey-based procedure for estimating population in small, rural areas. The procedure is a variation of the Housing Unit Method. It employs the...

A DAD Example: The Story of the Fourth Nuclear Power Plant in Taiwan
Over the past decade, nuclear power play an important role in help develop Taiwan's internationally recognized economy. The effort for putting the new nuclear power plant onto the grid...

Application of the Global Positioning System to Locating Remote Sites
The location of Near Field (NF) sampling stations, used for the radiological monitoring program portion of the site characterization phase of the Yucca Mountain Project, were determined...

Project on Contaminations-Radiation-Ecosystems-Health in Russia
We would like to discuss with you a project that we are currently developing, doing research upon and completing. In our report we represent the the following: - a few experimental data...

HWVP Compliance with the Hanford Site Solid Waste Acceptance Criteria
This report describes the Hanford Waste Vitrification project (HWVP), which will be located at the Haford Site. The Hanford Site encompasses a 560-mi2...

Tolerance Requirements for Remote Handling at the Hanford Vitrification Project
A new and innovative approach to installation of the many remote nozzles and electrical connectors that must be installed to demanding tolerances has been developed by the architect/engineer...

Yucca Mountain Site Characterization Project Exploratory Studies Facilities Construction Status
This paper discusses the progress to date on the construction planning and development of the Yucca Mountain Site Characterization Project (YMP) Exploratory Studies Facilities (ESF). The...

Project Control?The Next Generation
The Yucca Mountain Site Characterization Project (YMP) is the U.S. Department of Energy's (DOE) second largest Major System Acquisition Project. We have developed an integrated planning...

Mount St. Helens Recovery Project
Work began immediately after the eruption of Mount St. Helens to restore Columbia River navigation, provide 100 year flood protection for the downstream communities located along the Cowlitz...

Licensing and Permitting the Devil's Nose Project Under the 1990's Regulatory Conditions
Amador County is one of California's mountain counties of the western slope of the Sierra Nevada range in the north central portion of the state. The present population is estimated to...

Managing Government Contracts: Tips to Keeping Your Sanity
The key to managing large government projects is to divide it into smaller manageable pieces and organize it accordingly. Government projects are unique in that they require much more...

Evaluating Environmental Projects
Throughout the Nation, there is increased awareness of and concern for, environmental protection and restoration. Within the U.S. Army Corps of Engineers, new authorities are providing...

Wetland Engineering, Design, and Construction: State-of-the-Science and Research Needs
Local, state, and federal agencies, special interest groups, and individual landowners are undertaking wetland construction projects at a feverish pace to mitigate past and anticipated...

Strategies for Developing Major Capital Facilities
Siting, permitting, and mitigating impacts present many challenges during the development of major capital facilities. As a result of the need for public involvement, environmental review,...

The West Point Story?Chapter 2: Project Management Approach
In 1985, serving as the program lead, Metro contracted with Lewis Zimmerman Associates to conduct a formal facility planning effort for the West Point wastewater treatment plant. It was...

Small Area Water Demand Forecasting at the Salt River Project
The Salt River Project Small Area Water Demand Forecast (forecast) is designed to provide water resource planners with long-range water demand forecasts disaggregated by user type and...

 

 

 

 

Return to search