Development and Use of Stress Laminated Timber Deck Bridges
This presentation provides a brief overview of the concepts, development, research needs, economics and recent use of stress laminated timber bridge decks. Repeated articles on the serious...
Wind Tunnel Aeroelastic Model Study of the Baytown Bridge (Steel Alternative)
Analytical and full bridge aeroelastic model studies performed to assess the aerodynamic stability of the steel alternative Baytown Bridge over the Houston Ship Channel are described....
Vancouver's Skytrain Cable-Stayed Bridge?Dynamic Behaviour
This paper focuses on the dynamic behaviour of the Skytrain cable-stayed bridge under the action of earthquakes and wind. The 340 m span railway bridge is located on the west coast of...
Teleport: New Wave Engineering
Between $600 and $700 million will be spent on teleports now being planned in the U.S., presenting interesting challenges to civil engineers. Just as airports and seaports serve as collection...
Connecticut: A Success Story
The Connecticut Department of Transportation (ConnDOT) had warned the state legislature that its highways and bridges would continue to deteriorate without increased funds for inspection,...
A Strategic Approach to Planning and Financing Public Facilities
This paper presents a comprehensive, strategic approach to planning and financing public facilities by a toll road authority. Because the Authority finances projects through the sale of...
Strategic Planning/Management in a State Transportation Agency
This paper examines the concept of strategic planning/management as described in management literature and describes a recent application in a state transportation agency. The paper concludes...
Generating Alternative Financing Models for Urban Transportation: An Application of the Idea Machine
The purpose of this research was to examine how localities in Virginia could obtain funds for urban highway construction and maintenance, and indirectly, for mass transit from the so-called...
Impact Fees: Florida's Link Between Growth, Road Improvements, and Financing
Impact fees are one mechanism by which local governments can obtain additional revenue needed to construct major roads demanded by the consequences of new development. In Florida, the...
First Impulse Turbine in the U.S. Mining Industry
The United States Bureau of Mines has funded a research project to investigate the improvements made in the operation of mine refrigeration systems when a thermal energy recovery system...
The Ruedi Project?A Case Study
Ruedi Dam is a 285' high earthfill structure constructed in 1968 by the Bureau of Reclamation as part of the Fryingpan-Arkansas Transmountain Diversion Project. In November...
Retrofit Hydropower at Corps of Engineers' Dams
The Sacramento District of the U. S. Army Corps of Engineers is responsible for the review of retrofit hydropower by non-federal entities at 14 dams in the District. This review actually...
Evaluation of a Pump-Storage Hydropower Facility
This paper summarizes the findings of the evaluations conducted by faculty of the University of Missouri and outside consultants regarding the downstream effects of Harry S. Truman Dam...
Friant Power Project: Design and Construction?Non-Federal Power at a Reclamation Facility
Friant Dam, Millerton Reservoir, provides the principal water supply for the Friant Division Central Valley Project of the U. S. Bureau of Reclamation (Bureau). The dam is a 319-foot high...
Construction of Yellowtail Dam & Power Plant 63-65
The Yellowtail Unit of the Missouri River Basin project is located on the Bighorn River in south central Montana. The key feature of the unit is Yellowtail Dam which rises 525 ft. between...
Retrofitting Outlet Works of Existing Dams for Hydropower
This paper deals with three small hydroelectric plants installed at existing dams in California with moderately high heads (about 200 feet). In each case there was an overriding need to...
Economic Evaluation of Alternative Electric Power Developments
A hydroelectric-dominated power system and a thermal-dominated system represent different ways of meeting total electric demand, but with materially different cash flow patterns. This...
Hoover Dam Plus Fifty Years Equals El Cajon Dam
The completion of El Cajon arch dam on the fiftieth anniversary of the completion of Hoover Dam has given the opportunity to compare design and construction of two concrete arch dams constructed...
Infrastructure Development and Turbine Building
Aggressive development schedules which characterize many projects imply a degree of construction management know-how or alternatively, may say something about the state of the industry...
HydroMAX; Computerized Hydropower Scheduling
The New England Power Exchange (NEPEX) is currently using the HydroMAX Program to schedule daily hydropower operations for the 17 stations in the 11,250 square mile Connecticut River Basin....