Mt. Tabor Hydroelectric Project
In 1980 the engineering staff of the City of Portland Bureau of Water Works identified several potential hydroelectric sites in Portland water supply and distribution system. The Mt. Tabor...

Calaveras Pipeline Hydroelectric Project
The Calaveras Public Utility District (San Andreas, California) has a pipeline connecting its water treatment plant to the San Andreas Reservoir. By reducing the flow rate in the system...

Miramar/Alvarado Hydropower Projects
The San Diego County Water Authority (SDCWA) was organized in 1944 to provide imported water to member agencies in San Diego County. The 24 member agencies supply 90 percent of the water...

Low Head Hydroelectric Development on Madera Canal
The Madera-Chowchilla Power Authority with cooperation from the U. S. Bureau of Reclamation has been successful in the development of four hydroelectric plants at five head drops on the...

Re-Use of Civil Structures Make Norway Hydro Possible
Utilization of abandoned civil facilities made the addition of 1,800 KW to an operating 3,200 KW hydro plant of the City of Norway, Michigan Light and Power feasible. Work consisted of...

Two New Machines for Ultra Low-Head Hydropower
This paper outlines the development of two new types of positive displacement ultra low-head hydropower machines, the AUR Water Engine (AURWE) and the Salford Transverse Oscillator (STO)....

Hydropower on a Wastewater Plant Outfall: Point Loma Hydro Project
The plant is on a bluff 90 feet above the Pacific Ocean where the primary treated effluent is discharged through a 2-mile-long (3. 2 kilometer) outfall pipeline. The head was previously...

North Fork Hydro Electric Power Station
Lake Hemet Municipal Water District has recently installed a hydro power station capable of producing approximately 200 KW of power during years of normal flow and 600 KW during periods...

Non-Federal Hydropower Development at Federal Facilities
The opportunities are available for meaningful coordination among hydropower developers, consulting engineers, and Federal, State, and local agencies to promote comprehensive development...

FEM-Flow Analysis in Hydraulic Turbomachinery Runners
Finite element calculations of the flow through distributor and runner of hydraulic turbomachines are presented. The method is quasi-3D and inviscid, but the deviations from a potential...

Uncertainty Analysis of Field Turbine Performance Measurements
This paper presents comprehensive uncertainty analyses of two different flow measurement methods for field tests on turbines. The 'water to wire' efficiency was...

A Review of the Cross-Flow Turbine
The historical development of the cross-flow turbine is briefly presented together with a summary of the well-documented one-dimensional theory. Two-dimensional aspects of runner design...

Dolores Pumped-Storage Unit?A Case Study in Planning
The Durango Projects Office of the U. S. Bureau of Reclamation (Reclamation) conducted a pumped-storage investigation from 1981 to 1983 on a site in southwestern Colorado. This paper describes...

Unique Civil Engineering Features of the Balsam Meadow Pumped-Storage Project
The Balsam Meadow Pumped-Storage Project for the Southern California Edison Company is located in the Sierra Nevada Mountains approximately 55 miles northeast of Fresno, California. The...

Innovative Approach to New Water Supply/Power Development
Since the first deliveries made by the State Water Project (SWP) in the early 1960's the State of California has become known worldwide as a pioneer in the development of...

Friant Power Project: Design and Construction?Non-Federal Power at a Reclamation Facility
Friant Dam, Millerton Reservoir, provides the principal water supply for the Friant Division Central Valley Project of the U. S. Bureau of Reclamation (Bureau). The dam is a 319-foot high...

Construction of Yellowtail Dam & Power Plant 63-65
The Yellowtail Unit of the Missouri River Basin project is located on the Bighorn River in south central Montana. The key feature of the unit is Yellowtail Dam which rises 525 ft. between...

Roller Compacted Concrete and Tunnel Boring Machines?Two Tools for Designers and Planners
Two tools that have come into use fairly recently are roller compacted concrete and tunnel boring machines. These new tools can significantly affect the ability to make new projects cost...

The Diamond Fork Power Development Experience
Federal water development agencies are, to varying degrees, currently seeking financing partnership arrangements with states and other non-federal entities for up-front construction and...

Financing the Town Bluff Hydropower Project
The Town Bluff Dam Hydropower Project is the first new Federal hydropower project to be completely financed by a non-Federal entity where all of the construction funds would be provided...

 

 

 

 

Return to search