Vibration Problems of Penstock Piping for a Vertical Tubular Hydraulic Turbine
Excessive vibration amplitudes were experienced in the vertical gated tubular units at the Great Falls Hydroelectric Project located in the City of Paterson, New Jersey. Vibration amplitude...

Hydro Turbine Submergence
The elevation of a hydro-electric turbine above or below tailwater is based on hydraulic model studies to determine the critical sigma, defined as the ratio of barometric pressure plus...

Turbine Efficiency Measurements by the Pressure-Time and the Current-Meter Method at Paugan
Paugan generating station was built in the 1920s. Although the generators were converted from 25 Hz to 60 Hz in the mid 1950s, the original runners were in place until recently when a...

Transient Analysis of the Finchaa Hydroelectric Project
An iterative computer simulation procedure called LIQT (Liquid Transient), which performs simulations of hydraulic transients in closed conduit hydro-power systems, is used to estimate...

Fluctuating Pressure Measurements on a Large Hydro Turbine
The New York Power Authority is investigating the feasibility of upgrading the thirteen 150,000 kW turbines-generators at the Robert Moses Niagara Power Station to improve efficiency and...

Predicted and Observed Axial Behavior of Piles
Results of a Pile Prediction Symposium
This publication presents the results of a pile capacity event that was held at the Lakefill site on the Evanston Campus of Northwestern University in conjunction with the 1989 Foundation...

SPIDA Method for Reinforced Concrete Pipe Design
The required supporting strength of buried pipe is affected by the total load that is imposed upon the pipe and the manner in which the pipe is supported by the surrounding soil. The installation...

Creative Application of Materials Engineering
Society's demand for an aesthetically pleasing and safe constructed environment, along with the construction industry's higher and higher costs, dictate that...

Stabilizing a `Mann'-Sized Sinkhole
On Sept. 21, 1988, a sinkhole suddenly developed beneath a transmission/distribution effluent pipeline on Mann Road in Orange County, FL. Initially it measured 30 ft in diameter and 8...

Beam-Supported Slabs Subject to Edge Loading
A model is presented which allows a designer to estimate stiffnesses required to provide a given critical buckling load in beam-supported slabs subjected to biaxial edge loading, such...

Optimal Design of Small-Scale Hydro Projects
A nonlinear programming model is developed in this study to determine optimal pipe size, the type and number of turbines and the installed capacity for small scale hydro projects. The...

Appropriate Design and Construction of Conduits for Small and Mini Hydropower
The success of smaller hydro schemes often lies in identifying feasible and economic waterway systems to develop relatively high heads between low intake weir and powerstation. This paper...

Isabella Project?Retrofit of Existing Tunnel
This paper explains conceptual methods of reinforcing and lining the section of the existing tunnel downstream of the three control gates to the exit portal and bifurcation for the power...

High Pressure Grouting of the Bath County Tunnel System
A major grouting program was completed at the Bath County Pumped Storage Project between March and September 1985. High pressure grouting for seepage reduction was completed in a total...

Fretting Corrosion on Large Split Thrust Bearing Runners
In the early fifties interfacial slip was measured on laboratory models. Design improvements, resulting from these tests, were incorporated into later machines. These improvements appreciably...

Our Municipal Water System Has Power
Hydroelectric potential exists in the Boulder, Colorado municipal water system. Excess pressure is developed in the water system because the water originates in the Rocky Mountains, west...

Grout Supports Brooklyn Tunneling
At the Red Hook project in Brooklyn, microfine cement grout was injected from the surface to support underground tunneling. The hand-dug tunnel was built to connect to sewer pipes. Subsurface...

A Station With a View
The Port Authority TransHudson Corp. (PATH) is renovating and expanding Exchange Place station, the first stop in New Jersey across the Hudson River from lower Manhattan. To be completed...

The MPSP System: A New Method of Grouting Difficult Rock Formations
In unstable rock masses the traditional stage grouting methods may prove impractical or ineffective. A recent innovation has been the Multiple Packer Sleeved Pipe (MPSP) System. Akin to...

Frequency Domain Site Response with Pore Pressure
A frequency domain analysis for seismic site response and liquefaction potential is developed. The analysis is based upon a nonstationary random vibration theory. The model uses an effective...

 

 

 

 