Prediction of Fine Sedimentation in Small Marinas
Shoaling due to fine, cohesive sediment deposition in small marina-type basins is governed by basin geometry, hydrodynamic factors and sediment load in outside waters. An easily programmable...
Macro Data Acquisition Systems on Minicomputers
Selection of the proper minicomputer for a real-time data system is a careful design process based on system requirements. Hardware should be purchased after requirements are set and not...
Innovative Engineering Completes Dredge Spoil Disposal Facility
A large dredge spoil facility was completed for the Fort McHenry Tunnel that received 3.5 million cu yds of dredged material, and was constructed so that it could be converted into a port...
Port of Seattle Seismic Waterfront Design
This paper describes the soil seismic design process, using the design developed for a concrete apron project at Terminal 20 as an illustration. Damage by the 1965 earthquake is described....
Seismic Response of Port and Harbor Facilities
A research program compiled information regarding the behavior of port and harbor facilities during past earthquakes. The potential for significant damage to port and harbor facilities...
Lateral Load Tests of Piles in Sloping Rock Fill
A new container wharf constructed at the Port of Los Angeles features vertical prestressed concrete piles to provide both vertical and lateral support. A rockfill embankment used to allow...
Pile Foundation Movements During Construction
Two case histories concern a shipyard wharf and work bay in Los Angeles harbor and an oil refinery expansion in Sumatra, Indonesia. The case histories provide further data on the nature...
Monitoring of an Ocean Dredged Material Disposal Site
The Tampa Harbor Project involves deepening and widening approximately 50 miles of existing shipping channel in Tampa Bay, Florida, with the removal of approximately 70 million cubic yards...
Systems for Reducing Sedimentation in Berthing Facilities
Five systems are described which can be used to reduce sedimentation in harbor berthing areas. These systems, which are alternatives to conventional dredging, are based on either the resuspension...
A Methodology for Open-Water Disposal Site Selection
Pascagoula, Mississippi, is the major industrial region in coastal Mississippi. The existing project, completed in 1965, provides for waterborne transportation from the Gulf of Mexico...
Charlotte Harbor Beach Nourishment
The project consisted of dredging approximately 300,000 cubic yards (229, 380 cubic meters) of material, utilizing a seagoing hopper dredge, from the entrance channel of Charlotte Harbor,...
Management Plan for Dredged Maintenance Material
The Mobile District Corps of Engineers is responsible for the maintenance of an authorized Federal deep-draft navigation project at Pascagoula Harbor, Mississippi. The development of the...
Long-Term Planning for Dredged Material Disposal
The dredged material produced from maintenance of the channel in Upper Mobile Harbor (UMH) is disposed into confined upland disposal areas provided by the project's local...
Long-Term Maintenance Dredging Permits - Florida's New Approach to Regulation
Previous approaches to regulating maintenance dredging activities in Florida generally have been myopic and failed to gather information that adequately reflects the needs for environmental...
Long-Term Maintenance Dredging PermIts--Florida's New Approach to Regulation and Its Implications for Federal, State, and Local Reforms
Florida has developed a long-term maintenance dredging permit process to reduce problems in obtaining regulatory approvals. Under Florida's new program, the term of the permit...
Draghead Designs vs. Production
This paper discusses the development and design of draghead configurations for silt materials and describes a testing program designed to determine the most efficient range of the controllable...
Dredging Permit, a Case History
A case history of the federal, state and local permitting process for the dredging and disposal of dredged material of a tanker/barge terminal in Boston Harbor is discussed. The dredging...
Dredging for a new Port - Puerto Bolivar, Colombia
A major coal export terminal at Bahia Portete, Colombia, is being developed as part of the Cerrejon Coal Project - North Zone, where one of the world's largest coal mines...
Feasibility Study of Use of Dredged Material as Sanitary Landfill Cover in the New York/New Jersey Harbor Area
The feasibility of use of dewatered dredged material as cover material at landfills in the New York/New Jersey Harbor area has been investigated by the New York District, U. S. Army Corps...
Wetland Creation in Baltimore Harbor
Three areas of Baltimore Harbor were examined for use as wetland sites by Interstate Division for Baltimore City. Each site presented unique and interesting challenges to design. Economic...
Return to search