Three-Dimensional Stability Analysis of Carpenter Dam
This paper describes the three-dimensional stability analysis of Carpenter Dam. The presence of keyed construction joints between dam monoliths at Carpenter Dam can significantly affect...
Reliability Analysis of Navigation Structures
Methods for probabilistic stability analyses of concrete monoliths at hydraulic structures were developed and tested. Numerous analyses were performed using data from six actual structures...
Roller Compacted Concrete for Embankment Overtopping Protection
In the first National Dam Safety Inventory and inspection performed by the Corps of Engineers, the majority of deficiencies found were related to the inability of the project to retain...
Construction of CCM Overtopping Protection on Three Parkway Dams
Cellular concrete mat (CCM) systems have been installed as overtopping protection on three small embankment dams along the Blue Ridge Parkway. Based on field tests by others and on the...
Saylorville Spillway: Emergency to Service Spillway
The spillway for Saylorville Lake located on the Des Moines River, 12 miles north of the city of Des Moines, Iowa, a large metropolitan, was designed as an emergency spillway. Due to subsequent...
Mud Mountain Dam Concrete Cutoff Wall
Mud Mountain Dam is an earth and rockfill flood control dam on the White River. The dam is located approximately 50 km southeast of Seattle, Washington. The dam was constructed in 1941...
Landslide Stabilisation at the Clyde Power Project, New Zealand
The Clyde Power Project is a hydro electric development on the Clutha River in the South Island of New Zealand. A wide range of stabilization measures have been used to treat several large...
The Stabilization of Concrete Dams by Post-Tensioned Rock Anchorages: The State of American Practice
Permanent post-tensioned rock anchorages have been used for over twenty years in America to stabilize existing concrete dams and their appurtenant structures. This paper provides a state...
Bond Stress Test on Rock Anchor in Clayey Siltstone
Seventy five rock anchors with design loads of 556 to 2040 kips were required for the 1000-foot long, 125-foot high, concrete gravity, Lake Lynn Dam to comply with current FERC engineering...
Rehabilitation of Crescent and Vischer Ferry Dams?Construction Techniques & Problem Solutions
This paper reviews some of the problems encountered during the rehabilitation of the Crescent & Vischer Ferry Dams and the techniques used to comply with strict water level regulations...
Prestwood Lake Dam Rehabilitation
The Prestwood Lake Dam located in Hartsville, South Carolina is owned by Sonoco Products Co. It originally was a wood structure built in 1895. That structure was washed out by a hurricane...
Testing and Evaluation of High Capacity, Multi-Strand Rock Anchors for Lake Lynn Dam
Seventy five rock anchors with design loads of 556 to 2040 kips were required for the 1000-foot long, 125-foot high, concrete gravity, Lake Lynn Dam to comply with current FERC engineering...
Coolidge Dam Abutment Stability and Stabilization
This paper focuses on left abutment stability assessments and stabilization measures at Coolidge Dam, Arizona. Initial assessment of abutment stability was based on limited rock strength...
Conversion of a Concrete Slab and Buttress Dam to a Gravity Dam
The 58-foot high, 425-foot long, Ambursen-type, concrete slab and buttress, Gorge Plant Dam, which has a 120-foot long overflow spillway near the center, was converted to a concrete gravity...
Seismic Rehabilitation of Sardis Dam
Extensive subsurface investigation of the embankment dam revealed the existence of a weak layer of silt and soft clay in the original topstratum clay underlaying the upstream shell of...
Stability of Embankments, Fills and Structures at the Bad Creek Project Under Static and Dynamic Loading
Duke Power was faced with the problem of using explosives to assist in removing a sensitive, saturated embankment cofferdam supported on a large rock plug. The first phase of the work...
Rehabilitation of the Deep Creek Lake Dam
This paper presents the rehabilitation design for upgrading the Deep Creek Lake dam. The Deep Creek dam is a rock fill dam, 92 feet (28 m) high and 1290 feet (393 m) long, and constructed...
Accelerator for Shotcrete Based Amorphous Calcium Aluminate
The authors developed an accelerator based on amorphous cacium aluminate named NATMIC for shotcrete. In Japan, accelerator based amorphous calcium aluminate are widely used in shotcrete...
Steel Fiber Reinforced Shotcrete?An End-User Prospective
Nearly 15 years of experience demonstrates that steel reinforcing fibers in shotcrete offer considerable advantages to all end-users: designers, contractors and owners. These include demonstrable...
Large Scale Testing of Shotcrete
A large scale test program was carried out to evaluate the relative roles of steel fiber and mesh reinforced shotcrete for hard rock stabilization. The most realistic conditions in a tunnel...