Waste Phosphatic Clay Disposal in Mine Cutsr
Research was undertaken to assess the applicability of waste clay disposal back into phosphate mine cuts. The pit was monitored for two years with measurements of clay surface elevation,...

Centrifugal Modeling of Phosphatic Clay Consolidation
As a by-product of beneficiation, quantities of dilute clay slurry are produced which are stored in retention ponds. One method of accelerating consolidation is to surcharge the clay with...

Grouting Rehabs Earth Dam
To accommodate increased storage needs the Pennsylvania Power & Light Company had to reactivate a fly ash basin and raise an adjacent embankment dam. However, seepage through the...

Monitoring of an Ocean Dredged Material Disposal Site
The Tampa Harbor Project involves deepening and widening approximately 50 miles of existing shipping channel in Tampa Bay, Florida, with the removal of approximately 70 million cubic yards...

Systems for Reducing Sedimentation in Berthing Facilities
Five systems are described which can be used to reduce sedimentation in harbor berthing areas. These systems, which are alternatives to conventional dredging, are based on either the resuspension...

Thalweg Disposal: Demonstration of an Alternative
Disposal of dredged material in the main channel, or thalweg, is an alternative disposal option for maintenance dredging. The material dredged from the Upper Mississippi River is clean...

Offshore Dredging - Is it still Cost Effective for Beach Restoration?
Offshore dredging has been the source of sand for beach restoration in southeast Florida since Broward County constructed the first project in Pompano Beach in 1970. However, with increasing...

Land Application of Dredged Material at Port Manatee
Maintenance dredging of approximately 600,000 cu yd of highly plastic clay was conducted in October 1983. This material was deposited on a nearly 200 acre tract of farmland in a depth...

Efficiency of Capping Contaminated Dredged Material
The ability of capping with sand to chemically and biologically isolate contaminated dredged material was investigated using large scale (250 l) laboratory reactor units. Tissue analyses...

Draghead Designs vs. Production
This paper discusses the development and design of draghead configurations for silt materials and describes a testing program designed to determine the most efficient range of the controllable...

Open Water Disposal for Marsh Creation James River, VA
There is a need for close cooperation between design and construction of levees on soft foundation for containing dredge material. The scope of this study included marine exploration,...

Implementation of EPA/Corps Site Evaluation Guidance
Past site evaluations have resulted in expensive and time-consuming field studies and a nationwide delay in final designation of interim sites. Recognizing the problem, a joint Corps/EPA...

Agricultural Crop Production and Quality Effects when Soils are Amended with Dredged Lake Sediments
Lake renewal achieved by pumping loose sediment from the lake bottom requires a disposal area for that sediment and the associated water. Application of this sediment to agricultural land,...

Placing of Impermeable Underwater Membranes
An impermeable underwater membrane has been applied successfully in the construction of a lowered road section in the Netherlands. In this paper the construction technique is discussed...

Fabric-Reinforced Dikes, Craney Island
Three fabric-reinforced test sections 300-, 400-, and 750-ft long were successfully constructed on very soft dredged material deposits within the Craney Island dredged material disposal...

Dredged Material Disposal Modeling - Chesapeake Bay
A plan to deepen the approach channels to Baltimore Harbor from 42 feet to 50 feet involves in part the overboard disposal of about 9. 5 million cubic yards of dredged material in the...

REMOTS Sediment Profiling at the Field Verification Program
Disposal of uncapped highly polluted Black Rock Harbor muds took place in April-May 1983 at a buoy located within the Central Long Island Sound Disposal Area in 62-66 feet of water. Baseline...

Acoustic Silt Density Measurement
Significant savings can be achieved on the costs of operations for the deepening and maintenance of navigation channels and harbor basins in muddy areas provided that computations are...

Habitat Development Using Dredged Material
Over the past eleven years, a number of environmentally and economically acceptable beneficial uses have been tested and developed using dredged material substrates. This work has primarily...

Case History: North Slope Alaska Hydraulic Dredging
Alaska's North Slope Borough, with the aid of dredging machinery consultant Michael Weston, and geotechnical consultant Rittenhouse-Zeman & Associates, has pioneered...

 

 

 

 