Using Project Management Techniques in Hydro-Relicensing
To answer a pressing need for managing today's complex process and requirements of hydro relicensing, Central Maine Power Company (CMP) has applied the principles of project management,...
Extensive Civil Penalties Apply?Lessons Learned Since Waterpower '89
Section 12 of ECPA authorized the FERC to assess civil penalties in enforcing Part I of the Federal Power Act and its implementing regulations, as well as the terms and conditions of hydropower...
Benefits and Applications of Modular Hydroelectric Pumped Storage
Hydroelectric pumped storage is the only proven and most efficient technology available for energy storage. It is used by utilities to provide peak and intermediate power and to optimize...
Feasibility of Adding Small Hydro to Federal Hydraulic Structures in the Upper Ohio River Basin
A national hydropower program exists in which non-Federal interests may develop power at Federal hydraulic structures which have that potential. This paper discusses associated considerations...
Lake Siskiyou Power Project
The Lake Siskiyou Power Project was constructed at the foot of the existing Box Canyon Dam on the Sacramento River in Northern California. Major project features included the construction...
Private Hydropower Projects: Exporting the American Experience
This paper addresses different aspects of exporting the American knowledge and experience in the private development of small-scale hydropower projects. It details the 'export'...
Technology Transfer for Small Hydro
The wide range of different definitions of what constitutes a small hydroelectric power plants is discussed and the conclusion is drawn that this definition should be based more on the...
Net and Hydroacoustic Monitoring of Fish Passage
In 1986 EPRI published a review of available fish protection technologies for use at hydroelectric facilities. One major conclusion of that study was that fish protection systems were...
Design of Powerhouse Spiral Case Considering Three-Dimensional Action
A commonly used approach of designing semi-spiral cases for Kaplan turbine installation using two-dimensional frames becomes unsuitable for large diameter turbines and/or high heads. The...
Hand Held Powerhouse Control Console or Portable Data Terminal
The Portable Data Terminal (PDT) is a very small light weight hand held computer terminal that communicates with the control system computer by radio. An operator monitors power plant...
A Hydroelectric Plant Operator's Assistant
This paper describes a PC based application designed to assist in the process of enhancing the performance of multi-unit hydroprojects. Optimization considerations, uses of the Operator's...
Measurements of Time Lag in Concrete Gravity Dam Foundations
Uplift measurements from eight large concrete gravity dams show that the time lag between an increase in headwater level and a corresponding increase in uplift pressure is insignificant....
Geotechnical Aspects of the Underground Excavations at the Kemano Completion Project
The Kemano Completion Project is the addition of four generators of 540 MW installed capacity to an existing eight-unit underground hydroelectric generating station owned and operated...
Soil Nails as Temporary Powerhouse Support
Newcastle Powerhouse was constructed as an underground structure with its top deck at the finished ground surface. The powerhouse is three-quarter circular and one-quarter square in plan....
An Alternative Approach to the Maximum Flood Concept
This paper outlines an alternative to the current approach for determining the maximum flood of river basins. The condition of the maximum flood is derived from the convolution integral...
Examples of Risk Assessment in Dam Safety Decision Making
Three examples of risk-based dam safety evaluations performed for dam users or operators are summarized. These studies were conducted by major U.S. engineering firms and involved experienced...
The Stabilization of Minidoka Powerplant and Dam
The rehabilitation of structures can pose numerous challenges to the engineer. The structure historical preservation, the benefit cost ratio of the rehabilitation, and the stability of...
Seismic Analysis of the Bonneville 1st Powerhouse
The Bonneville 1st powerhouse monoliths were constructed during the period of 1938 to 1942 and were designed against seismic loads using the old lateral coefficient method. The Corps of...
Estimating Uplift in Cracks in Concrete Dams
Results are presented of a three year research program on the modeling of uplift pressures in cracks in concrete gravity dams, and the effectiveness of drains in reducing those pressures....
Dam Stabilization/Modification at Lighthouse Hill and Schuylerville Hydropower Developments
Remedial measures including posttensioning of concrete structures, earth dike armoring, tainter gate modification and replacement of deteriorated concrete to meet federal and state hydraulic...