Tunnel Takes Cathodic Protection
Cathodic protection is nothing new for bridges and parking garages, but it has never been installed in a tunnel�until now. As part of a $15 million rehabilitation project, the method is...

Tying Back a Landslide
A slope covered with landslide debris is never the most desirable site on which to build, but sometimes it is the only one available. For the Forks of Butte hydroelectric power project,...

Manholes and Microtunneling
Contractors are for the Oakwood Beach Interceptor Sewer Project, on Staten Island, N.Y., were having difficulty. Glacial tills and a high water table made working 90 ft below the ground...

Put to the Test
In the construction industry, the concept of life-cycle cost applies not only to the infrastructure itself, but to the materials that go in to building that infrastructure. To improve...

In Too Deep
Urban excavation is fraught with risks and potential liability for engineers and contractors. Environmental issues (such as Superfund regulations and environmental impact statements),...

Settling Down Easy
In order to more fully participate in the international and Asian Pacific aviation network, it was decided to establish a highly efficient 24-hour a day operation at the New Kansai International...

Pressure Pipeline Design for Water and Wastewater
This committee report, Pressure Pipeline Design for Water and Wastewater, is a revision of the 1975 ASCE publication Pipeline...

Rethinking the Competitive Bid
Concern that the U.S. construction industry is losing its competitive edge is nothing new. Ironically, the problem is not so much rooted in foreign technical expertise as it is in our...

Decentralized Wastewater Management
With the discovery earlier this century that city squalor caused disease, we protected ourselves by piping raw wastes away. Later, when the discharge had transformed rivers into foul,...

Dome Over Orlando
The article describes Orlando's new City Hall, a 267,000 sq ft nine-story reinforced concrete tower, clad in granite-aggregate precast concrete panels and topped by a 120...

School Is In Session
Cost overruns, project delays and the city bureaucracy have given school construction a bad reputation throughout the U.S., particularly in urban centers. But as other construction markets...

PS 5 Sewage Lagoon Embankment Stabilization
In 1981 an embankment containing a three-cell wastewater treatment lagoon was constructed adjacent to the northern edge of the Pump Station 5 gravel pad on the Trans Alaska Pipeline System....

Winter Sewer Construction in Campbell Lake
This paper discusses the winter construction for replacement of the Campbell Lake portion of the Campbell Creek C-5 Trunk (C-5 Trunk) located in Anchorage, Alaska (see Figure 1). A previous...

Processed-Snow Foundation Design at the Summit of the Greenland Ice Cap
The design and construction of a processed-snow foundation berm for an elevated building located at the summit of the Greenland Ice Cap is described. Weather conditions and design provisions...

Environment One: A Master Plan Study for a New Scientific Research Station at the Geographic South Pole
The existing research station at the geographic South Pole is approaching the end of its useful life. This master plan study focuses on determining the technical and functional requirements...

Use of Rigid Insulation Below Grade for Roadways and Parking Areas
Minnesota Power's Herbert Service Center is located 3 miles north of downtown Duluth, Minnesota. The facility, constructed in 1967, consists of primary buildings, cold storage...

Treatment of Unstable Foundation Areas in Alaska's Pavement Management System
In the State of Alaska Department of Transportation and Public Facilities Pavement Management System (PMS) unstable foundation areas are defined as sections of roadway that experience...

Application of Ice/Structure Interaction Concepts to a Real Time Ice Risk Assessment Computer Model
The successful and safe operation of an Arctic offshore exploration structure greatly depends on the implementation of alerts procedures. In order to assess alerts levels, a computer model...

Risk Assessment for Groundwater Pollution Control
Prepared by the Groundwater Risk Assessment Task Committee for the Water Pollution Management Committee of the Environmental Engineering Division of ASCE. ...

Privatization Takes Flight
The number of air travelers in the U.S. is projected to double by early in the next century. Delays have also been mounting rapidly. Major airports around the world are facing the same...

 

 

 

 

Return to search