Cable Car Renovation Project: On Time and on Budget
San Francisco Municipal Railway officials had originally expected it would take three years to renovate the nine miles of deteriorated trackway and restore and seismically upgrade the...
Operations Improvement through Product Evaluation
Transit Managers today are involved in a battle to maintain the quality of their systems. This paper takes a close look at several problems and then suggests a cure that can be effective...
Construction Management: Dallas North Tollway Project
This article will attempt to illustrate the importance of flexibility of the design and construction inspection process to insure the project is constructed within the time and budget...
International and Educational Aspects of Watershed Management
International donor agencies involved in furnishing technical and economic assistance for increasing food and fiber production are focusing their attention towards rain-fed agricultural...
A Look to the Future in Watershed Management
The discipline of watershed management will continue as a viable specialized field as the scarcity, demand, and price of water increase in the future. Training of watershed managers should...
Tools for Managing Army Training Lands
Army land managers and planners are responsible for managing large, diverse parcels of training land for sustained use. The highly variable but often destructive training requires a systematic...
Acid Deposition in the Wind River Mountains
National attention has been focused on the discovery of acidified lakes in the Adirondack Mountains of New York and elsewhere in New England. It is commonly believed that the West, in...
Closed Negotiations?Out with the Poker Players
The paper describes the closed negotiation process employed by one owner/client, the U. S. Army Corps of Engineers, in procuring firm, fixed price design service contracts. Although not...
Advantages of Standard Contract Forms
The standard forms produced by the Engineer's Joint Contract Documents Committee (EJCDC) offer many advantages to Engineers and others involved in the negotiation and preparation...
Techniques of Negotiation
Three primary qualities are necessary for effective negotiation: knowledge, attitude, and skill. The author's firm has successfully used a negotiating team approach. This...
Computer Applications in Grouting
The first use of computers during foundation grouting was tried by the Bureau of Reclamation on Ridgeway Dam in Colorado. It was very useful in monitoring real time down hole conditions...
Probability of Stability Design of Open Pit Slopes
Uncertainty and risk have always been associated with mining. This is evidenced in the common mining terminology of proven ore, probable ore, and possible ore. From a geotechnical standpoint,...
Prediction of Highway Construction Noise Levels
A model for the prediction of noise levels from highway construction operations has been developed under sponsorship of the Federal Highway Administration (FHWA). Noise sources are geometrically...
Composite Bridge Design in Germany
A span length between 40 m and 12 m has been regarded as optimal up to the mid-60's for a composite design to compete with prestressed concrete or steel alternatives. With...
SRC Elevated Station Structures for New Bullet Trains
SRC Steelframe reinforced concrete structures were utilized on several station buildings for the Japanese National Railways bullet trains. This paper presents an outline of the dimensions...
Checking Off CADD Priorities
Diving head on into new computer aided design and drafting (CADD) hardware and software without considering their effects on firm or university's operation is as bad as ignoring...
Challenges to Civil Engineering Educators and Practitioners?Where Should We Be Going?
The papers included in this publication present an overview of the current state of civil engineering education and resolutions for future development in the field. Six key areas are covered:...
Organization and Management of Public Transport Projects
Transit development projects are undertaken to help satisfy escalating transportation needs in modern cities. The projects address an array of technical, social, and environmental considerations....
Computer Impacts on Water Resources Engineering
Computation capability has increased by a factor of one million over the past 30 years and has contributed greatly toward data management and the application of available technology to...
Computers in a Planning Context: Another Reality
Over the past twenty years water resources planning has seen a great increase in the development of computer methods of analysis. This has transformed the way the hydrology, hydraulics,...