Optimal Real-Time Control of Hydroelectric Power Plant Using Dynamic Programming
In this paper, an approach of optimal real-time control of hydroelectric power plant operations is presented. The methodology is based on a dynamic programming technique where the original...
Hand Held Powerhouse Control Console or Portable Data Terminal
The Portable Data Terminal (PDT) is a very small light weight hand held computer terminal that communicates with the control system computer by radio. An operator monitors power plant...
A Hydroelectric Plant Operator's Assistant
This paper describes a PC based application designed to assist in the process of enhancing the performance of multi-unit hydroprojects. Optimization considerations, uses of the Operator's...
Ferroresonance & the Snettisham Hydroelectric Project
Key system features of the Snettisham power plant in Alaska will be highlighted along with a discussion of the operational problems encountered due to a ferroresonant condition. The project...
Voltage Regulator Influence on Generator System Stability
During initial startup of a generator system, it is not uncommon to witness generator voltage instability. Most of the time, the solution is reduced to returning the stability control...
Validation Studies on Indexed Sequential Modeling for the Colorado River Basin
A method called indexed sequential modeling (ISM) has been developed by the Western Area Power Administration to estimate reliable levels of project dependable power capacity (PDC) and...
Operation of Hydropower Plants Considering Daily Streamflows
Operation of hydropower plants is a sequential decision process often modeled as a dynamic programming problem. Typically, such formulations consider monthly stages assuming that monthly...
Streamflow Gaging in a Remote Area Using Cellular Telephone Telemetry
A case study will be presented describing the utilization of cellular phone technology in a remote sensing situation. Because expected annual energy estimates are vital in planning small...
Consideration of Sedimentation on Hydropower Projects
Experience gained by analysis of a number of hydropower projects throughout the world leads to the conclusion that it is necessary to consider sediment related aspects in the design and...
Case Study: Steele Creek Dam Safety Analysis, Bristol, Tennessee
Steele Creek Dam creates a small recreational park lake before discharging into Beaver Creek a few hundred yards below the dam. Existing homes and trailers downstream from this junction...
Risk Analysis Applications for Dam Safety
Dam safety modifications are intended either to reduce the likelihood of the adverse consequences of dam failure or the magnitude of adverse consequences. For instance, widening a spillway...
Seismic Analysis of the Bonneville 1st Powerhouse
The Bonneville 1st powerhouse monoliths were constructed during the period of 1938 to 1942 and were designed against seismic loads using the old lateral coefficient method. The Corps of...
Cone Penetration Testing: Cost Effective Soil Exploration
On reviewing the 1987 Part 12 Dam Safety Inspection Reports for the Wisconsin River Power Company's Petenwell and Castle Rock Dams, the Federal Energy Regulatory Commission...
Effects of Uplift on a Gravity Arch Dam
This paper evaluates the behavior of a gravity arch dam when subjected to normal static loads and internal hydrostatic pressure (uplift). The ability to model uplift has become necessary...
Brule Hydroelectric Project Inflow Design Flood Study
In 1987, Wisconsin Electric Power Company (WE) was directed by FERC to provide additional spillway capacity at it's 63-foot (19 m) high Brule Dam. Original spillway capacity...
Analysis and Stabilization of Ambursen Dams?Two Case Studies
Case studies are presented about the analysis and rehabilitation of two slab-and-buttress (Ambursen) dams. The paper discusses the investigation techniques used, including sampling of...
Three Dimensional Modeling of Concrete Dams with Cracks Using Boundary Element Methods
Determining uplift pressure distributions in cracks in a concrete dam requires coupling between crack hydraulics and the stresses and displacements occurring in the rock and the concrete...
Hydraulic Design and Development of Propeller Replacement Runner for R. H. Saunders
This paper outlines the hydraulic design for the R.H. Saunders replacement runner. The six-bladed propeller runner was numerically optimized based on 3-dimensional flow simulation. After...
Dardanelle Turbines
The Dardanelle turbines located at river mile 205.5 of the McClellan-Kerr Arkansas River Navigation System, are experiencing an unusual amount of wear in the blade trunnion bushings. Oil...
Decision Support for Colorado River Operations
The United States Bureau of Reclamation (Reclamation) uses a simulation model known as the 24-month Study Model for planning monthly and seasonal operations for the Colorado River Basin....