Concrete Face Rockfill Dams of the Winneke Project
Two of the three dams forming the Winneke Reservoir, near Melbourne, Australia, are concrete face rockfill dams. A minor dam forming the sludge storage pond for the project's...

Design and Performance of Shiroro Rockfill Dam
Shiroro Dam, constructed across the Kaduna River in Nigeria, is a rockfill dam with reinforced concrete facing. The dam was completed in late 1983, and reservoir impounding started in...

Design Features of Salvajina Dam
Salvajina dam is the second highest concrete face rockfill dam currently in service in the world. The characteristics of the foundation of the toe slab vary from fresh, sound and little...

Performance Prediction for Removal of Odorous Organics From Drinking Water by Adsorption
The authors address three questions: What do packed bed filters remove from suspension in water treatment plants? How do they accomplish this removal? How can this knowledge be used in...

Particles, Pretreatment, and Performance in Water Filtration
Relationships among raw water quality, pretreatment facilities, and the design of packed bed filters are presented and applied. The particle size, particle concentration, particle surface...

Physical Evaluation of a Buried Drainage System
The drainage problem in the 600,000 acre (1. 5 million ha) Westlands Water District (District), located in the Central San Joaquin Valley in California is that of a perched saline groundwater...

Water Quality Issues at Fossil Fuel Plants
This publication highlights proposed approaches and actual projects for dealing with such water quality issues at fossil power plants as water supply, water treatment, and the protection...

Distillery Wastes Treated and Recovered Energy Saves $1 Million/Yr
The waste treatment and energy recovery for the world's largest rum distillery (Bacardi Corp., San Juan, Puerto Rico) uses an aerobic digestion to treat distillery wastes...

Slurry Trenches for Containing Hazardous Wastes
Slurry trench technology has not advanced much during the past 10 years due to a lack in research and development, the excerbated litigious climate in the environmental protection field,...

Innovative Engineering Completes Dredge Spoil Disposal Facility
A large dredge spoil facility was completed for the Fort McHenry Tunnel that received 3.5 million cu yds of dredged material, and was constructed so that it could be converted into a port...

Civil Engineering: At the Center of Technology for Tomorrow
Between now and the year 2000 civil engineers have the opportunity, perhaps more than any other profession, to help create the monuments of our civilization. This will involve projects...

Assessing the Effects of Water Contamination
The threats to potable water are examined. An assessment of human ill effects of contaminated water requires a knowledge of the quality of water throughout the world and a corresponding...

How Should We Dispose Hazardous Wastes?
Our inability to successfully dispose hazardous wastes has led to extensive land, groundwater and surface water pollution. The question is not whether we have the technology to do the...

Superfund Cleanup Sites
Cleanups of four Superfund hazardous waste sites are described, two in Pennsylvania, one in Tacoma, Wash., and one in Globe, Arizona. The key chemical wastes were polychlorinated bipheynls,...

Probabilistic Characterization of Soil Properties
Bridge Between Theory and Practice
The two objectives established for these proceedings are: (1) to summarize the principles and procedures of probabilistic characterization of soil properties in a readily understood manner...

New Plant Treats River and Well Water
A new 16 mgd water softening plant at Elgin, Ill. is designed to treat raw water either from the Fox River or deep wells, or in any combination. Flexibility of the chemical feed systems...

Fast Tracking Milwaukee's Stormwater Cleanup
In building a massive sewer and treatment plant, Milwaukee solved legal and management problems. At the same time, the city speeded design and construction for the project. Triggered by...

L.A. Grapples with Changing EPA Regs
Environmental Protection Agency (EPA) studies indicate that between now and the year 2000 an additional $117 billion will be needed to accommodate projected growth and to meet water quality...

Water Supply
The Foothills Project adds 125 mgd (5.5 m�/s) to the Denver area water treatment capacity, and saved approximately $1 million in energy costs in the first year of its operation. The $163...

Caisson
The Jamaica Bay Water Pollution Plant was renovated and upgraded from l973-l983 and included sinking a 116 ft. x 105 ft. caisson 50 ft. deep adjacent to city streets and buildings. The...

 

 

 

 