Drilled Shaft Side Resistance in Clay Soil to Rock
An evaluation is made of available field load test data for the axial side clay soils to hard rocks. Conventional total stress interpretations by the alpha method are used to examine the...
Execution and Evaluation of High Capacity Caisson Load Tests in Glacial Deposits
As part of the Boston Harbor clean up project, the new 1,000 mgd Deer Island Sewerage treatment plant includes ten 240 feet high egg-shaped 'residuals' tanks. Contract documents called...
Bi-Directional Load Testing of Shafts to 6000 Tons
This paper describes the use of Osterberg cells (O-cells) to perform bi-directional load testing on full size production drilled shafts for a major bridge foundation near Owensboro, Kentucky....
Load Testing of Permanently Cased Drilled Shafts Founded in Hartford Shale
The axial and lateral load testing of three, 30 inch (76cm) diameter, permanently cased drilled shafts is analyzed herein. The prototype shafts were founded in (or on) Hartford Shale bedrock,...
Perimeter Load Transfer in Drilled Shafts in the Eagle Ford Formation
Results of six full-scale compression loading tests at four sites in the Dallas area are considered. Compressive strengths (qc) of the rock varied...
Side Resistance of Drilled Shafts in the Denver and Pierre Formations
Results of load tests on drilled shaft foundations in Upper Cretaceous shales are described and evaluated. Three load tests were conducted on shafts in the Denver Formation, in Denver,...
Behavior of Instrumented Model Piers in Manufactured Rock with a Soft Layer
A laboratory test apparatus has been used to study the side resistance of piers socketed into manufactured soft-rock masses. The results of four tests are reported, three of which included...
A Laboratory Procedure for Partial-Wetting Collapse Determination
Partial wetting results in partial collapse, which is linked to the reduction in soil suction caused by wetting. The laboratory procedure presented in this paper represents a modification...
Going International: Profit or Peril?
Six veterans of the international engineering and construction market discuss the financial risks of international work, including currency risk; expatriate living conditions; difficulties...
Vietnam: Worth Looking Into
If it is to enter the world economy, let alone play catch-up with the booming economies of some of its neighbors, Vietnam requires massive numbers of infrastructure projects: roads, bridges,...
Keeping Cables Calm
Cable vibration and corrosion are potential problems relating to cable-stayed bridges. Nonetheless, owners think their structural elegance is worth it, and increasingly longer cable-stayed...
Arches For A Parkway
The final phase of construction on the Natchez Trace Parkway (which follows a centuries-old 450 mi trail between Natchez, Miss. and Nashville, Tenn.) is nearing completion almost 60 years...
The Hazard In Using Probabilistic Seismic Hazard Analysis
Probabilistic seismic hazard analysis has been used extensively for major dams; nuclear power plants; liquefied petroleum gas installations; repositories for dangerous wastes; sensitive...
A Dome To Remember
Under intense pressure from all sides, a trio of engineering and architectural firms working in San Antonio, Tex., turned the political coal of a stadium everyone wanted to build (but...
Seismic Remediation for Earth Dams
Over the last 30 years or so, new analysis methods and case histories of dam performance in earthquakes have significantly changed our understanding of the severity of the earthquake hazard...
Calendar: Bridges 1994
Featured bridges are: Briggs Bridge (AK); Stone Arch Bridge (NY); Rio Grande Gorge Bridge (NM); Bridge Street Bridge (MI); Hennepin Avenue Bridge (MN); Egypt Pike Bridge (OH); William...
Laboratory Testing of Stone for Rubble Mound Breakwaters: An Evaluation
The quality of the final stone product hinges on the combination of two factors - rock properties and environmental conditions. The environmental conditions associated with production...
Service Records of Chicago District Breakwater Stone and How These Relate to Test Results
Breakwater stone production is limited to areas with geologic outcrops capable of producing large rocks. The most reliable breakwater stone is that which exhibits the highest degree of...
Quarry Inspection: A Geological Perspective
The need to use durable rock in building projects is becoming more critical as the costs of labor and materials rise. The Steering Committee of the 1991 Quarried Rock For Rubble Mound...
Roller Compacted Concrete Mix Design
This paper presents a concise and proven mix design process. It covers all the steps necessary to produce a good roller compacted concrete (RCC) mix design for mass and structural applications,...