Lessons Learned from Elk Creek Dam
This is the third of a series of papers published on the design and construction of Elk Creek Dam. The first paper discussed design and construction concepts to provide water tightness...
RCC Dam Construction?A Contractor's View
A contractor's view of RCC dam construction is presented. It begins with the principal construction elements and the challenge created by their interrelationships. Men and...
Economic Factors in Roller Compacted Concrete Dam Construction
This paper deals with some of the economic factors that designers and contractors need to consider in the design and execution of an RCC dam. Costs for the RCC portion of the Upper Stillwater...
Mixing and Delivery of Roller Compacted Concrete
Mixing and delivery of RCC are discussed. Both the design aspects such as variability and joint quality, and the construction aspects such as equipment capability and performance are covered....
Construction of Urugua-I RCC Dam
Considerations concerning the RCC construction process and its relation with the design and quality are analyzed. The paper contains topics related to the experience obtained at Urugua-i...
RCC Dam Design Concepts Versus Construction Conditions for Stagecoach Dam
The Stagecoach RCC dam was constructed using current state-of-the-art knowledge and the geotechnical approach to roller compacted concrete (RCC) mix design. The design was prepared in...
RCC Mixes and Properties Using Poor Quality Materials?Concepcion Dam
This paper discusses aggregate studies, mix investigations, and material property tests for the relatively poor quality materials available for use in RCC at Concepcion Dam....
Thermal-Structural Analysis Methods for RCC Dams
Current procedures for evaluating temperature control and the placement of contraction joints in roller compacted concrete dams are not always evaluated with the aid of detailed analysis...
Final Design and Construction of Gibraltar Dam Strengthening
The results of a 1983 safety evaluation of Gibraltar Dam indicated that the dam did not meet seismic safety standards. A remedial scheme involving the addition of a roller compacted concrete...
Santa Cruz Dam Modification
Santa Cruz Dam was the first concrete arch dam in the United States to be modified using an roller compacted concrete (RCC) buttress. Innovative techniques included forming the stepped...
Roller Compacted Concrete III
This proceedings,
The Heartbeat of the Artery
One of the most ambitious infrastructure megaprojects in recent memory, Boston's $5 billion Central Artery runs the gamut of civil engineering disciplines. Design, highway,...
Staffing Up for a Major Program
A nine-member construction management section must pilot a $335 million, multi-project capital improvement program over the next five years. Should construction management duties automatically...
An Overview of Segmented Offshore/Headland Breakwater Projects Constructed by the Buffalo District
Since 1977 the Buffalo District has constructed three segmented offshore breakwater projects and currently has one under construction. In addition, the District has recently completed...
Bay Ridge, Anne Arundel County, Maryland Offshore Breakwater and Beach Fill Design
Construction of the Bay Ridge shoreline protection project was completed in July 1991 and consists of eleven offshore segmented breakwaters with beach fill. The breakwaters, located about...
Laupahoehoe Harbor Planning, Design, & Construction
Laupahoehoe Harbor provides access to the fertile fishing grounds along the northeast or Hamakua coast of the island of Hawaii, Hawaii. The planning, design, and construction of Laupahoehoe...
Military Techniques for Expedient Repair of Earthquake Damaged Harbor Infrastructure
Logistical support of military forces in the theater of operations during conventional warfare by shipment of large volumes of containerized cargo requires sustained use of strategic port...
Design and Construction of Shinnecock Inlet, New York
Shinnecock Inlet is the easternmost of six coastal inlet which bracket the barrier island on the south shore of Long Island, New York. Through recent history, Shinnecock Inlet has exhibited...
South Jetty Scour Hole Stabilization, Ocean City, Maryland
Formation of a scour hole along the inlet side of the South Jetty at Ocean City occurred after jetty construction as a result of ebb tidal flow in the inlet. Analysis of historical bathymetry...
Design Considerations for Small Artificial Islands in Franks Tract, California
Small, artificially-created islands may provide significant recreation and habitat benefits. Costs, however, can also be high. The initial dollar cost of creating an artificial island,...