Evaluation of Structures by Dynamic Load Testing
The Frequency Sweep Method for the evaluation of structures by dynamic load testing was developed by the senior author. It is a non-destructive testing (NDT) method that was originally...

Bridge Inspection by Dynamic Loading Technique
This paper describes, a case study of the evaluation of the structural integrity of a New York State Thruway bridge using the dynamic loading technique. The study was undertaken in a effort...

Lift Bridge looks Like Sculpture
A lift bridge built in 1926 over the U.S. Canal at Kaukauna, Wis. was replaced by a sleek new lift bridge whose sculptured shape encloses all the machinery within welded steel box sections....

Hundreds of Bridges�Thousands of Cracks
In the past 10 years hundreds of welded steel bridges, most of them relatively new, have suffered thousands of cracks due to secondary stresses, that is, the cracks are caused by deflections...

Proposed Design Criteria for Composite Steel Deck Slabs
Composite steel deck slabs have continued to gain popularity; today they are one of the predominant means of floor slab construction in most typical buildings. The term 'composite...

Load-Carrying Capacity and Remaining Life of First-Built Composite Girder Bridge in Japan
Kanzaki Bridge, Osaka, Japan, was the first steel-concrete composite bridge built in 1953 to carry the Osaka Prefectural Road over Kanzaki River. The bridge was removed in 1978 after 25...

Design and Testing of a 400 Ft Span Plate Girder Bridge
The paper describes design features and testing of the Madawaska River Bridge. The bridge is unique in being the longest span plate girder bridge in Ontario, having continuous spans of...

Composite Bridge Design in Germany
A span length between 40 m and 12 m has been regarded as optimal up to the mid-60's for a composite design to compete with prestressed concrete or steel alternatives. With...

Composite Steel Deck Bridge: An Experimental Study
Composite steel decks with steel fiber reinforced concrete (SFRC) were developed, aiming to improve the durability of the deck pavement and to increase the rigidity of the deck plate in...

Dynamic-Fatigue Response of Continuous Composite Bridges
The dynamic response of continuous composite bridges and the influence of fatigue loading at resonance frequency on the structural response are investigated. It is shown that cracking...

Application of Preflexed Composite Beams to Continuous Bridges
A preflexed beam is a type of concrete encased steel beam of which prestressing has been introduced in the lower flange concrete. Recently, the preflexed composite beams were applied to...

Recent Research on Composite Structures for Building and Bridge Applications
Continuing research has been carried out at Lehigh University on composite structural members, joints, and overall systems. This paper summarizes the results of research on four selected...

Seminar Summary and Research Needs
All the papers presented in the technical sessions of the seminar are summarized and, in some cases, commented upon. The needed research in composite and mixed construction is described....

Timber Bridge Decks
The portion of the nation's 500,000 bridge decks that are made of timber has been declining for years, as the old timber ones on secondary road bridges are rebuilt, in most...

High Strength Steel
A Wall Street Journal story in January 1984 described a number of bridges, buildings, automobiles, buses and other structures made of high-strength...

A Road to Recovery
Inspections of the Golden Gate Bridge revealed that the bridge had localized corrosion near its expansion joints, corrosion of its reinforcing steel, and was severely contaminated with...

Risk Analysis for Ship-Bridge Collisions
The authors have developed a propriety software package which has been successfully used to perform risk analyses for several high-level bridge structures across major waterways in coastal...

Coping with Litigation
Engineers should learn legal philosophy, even though it seems unrelated to traditional technical practice. Monitoring changes in legal theory that may increase engineers'...

Floating Bridge for 100 Year Storm
In 1979 the west half of the Hood Canal Floating Bridge, built in 1960, in Seattle broke up and sank during a storm that lasted eight hours with winds of 80 mph and gusts over 100 mph....

Record Bridge Replacement
Jacks Run Bridge had to be rebuilt in one year instead of the usual two to three. So the Pennsylvania Department of Transportation spearheaded the quickest replacement of a major bridge...

 

 

 

 

Return to search