Calibration of Beni-Mazar Movable Bed Model
A sand-bed model representing a reach of the Nile River was constructed to study alternative solutions to maintaining the navigation channel. Flume tests were carried out first to determine...

Fluvial Recharge of Sand Mining Pit
Accuracy in modeling fluvial processes becomes increasingly important as development occurs along waterways. The FLUVIAL-12 (1, 2) model is used to simulate the recharge of sand mining...

CPM Techniques for Claims Avoidance and Preparation
Virtually all major construction claims consist of some aspects of delay, disruption or acceleration. Since all of the foregoing relate directly to the timing and sequencing of the project...

The Benefits of U.K. Guidance for Temporary Works
In British contracts the Contractor is responsible for the design and execution of temporary works unless the Design Engineer or the Client expressly instruct how the work is to be undertaken...

Legal Principles and Theories
Legal issues are intertwined with all aspects of the technical considerations relating to temporary structures. This paper presents an introduction to the legal theories which relate to...

Historical Background
Discussions on payments for encountering unexpected conditions in construction commenced in 1960 and subsequent programs were presented in 1963, 1989 and 1991. The current symposium contains...

Who Pays for the Unexpected in Construction? A Heavy Construction Contractor's Viewpoint
The complex question of who pays for the unexpected in construction is analyzed using several examples from experience. In addition to the unexpected being due to subsurface conditions,...

Who Pays for the Unexpected in Construction??Owner as Engineer's Point of View
In the case of an unexpected discovery or development, it potentially may evolve into a three-cornered dispute among the Owner, Engineer, and Contractor. Frequently, it may become a two-sided...

Who Pays for the Unexpected in Construction?
Unexpected events of major concern result from voluntary risks taken by one or more of the parties to a construction contract. The party taking the risk should reap the reward or pay the...

Who Pays for the Unexpected in Construction: The Geotechnical Contractor's Point of View
Unexpected conditions are inherent in most construction projects and often lead to claims and legal action. Contract risk avoidance language force owners, engineers and contractors to...

Who Pays for the Unexpected in Construction
A grouting contractor's point of view on who pays for the unexpected in construction is presented. Because grouting can be used as an alternative for other construction procedures,...

Who Pays for the Unexpected in Construction??The Lawyer's Point of View
Encountering the unexpected is to be expected - it is one of the risks inherent in construction. While encountering the unexpected cannot be completely prevented, steps to (1) reduce the...

Who Pays for the Unexpected in Construction?An Architect's Viewpoint
As an Architect, who in the first instance is contractually obligated to address the full range of design discipline services, the question of 'who pays for the unexpected...

Who Pays for the Unexpected in Construction: Hi-Rise Engineers Point of View
The unexpected in high-rise construction can be traced to design criteria evolving from environmental models and probes, as well as 3 general problems dealing with quality control in contract...

Who Pays for the Unexpected in Construction? The Law, the Courts and ADR
If the question as to who pays for the unexpected in construction has to be answered because the parties have not amicably resolved a particular dispute, that answer will depend upon the...

Incentives for Technological Innovation in Construction
Why innovate in construction? The answer to this frequently asked question is critical for the future of the U.S. engineering and construction industry. One reason for this is the multitude...

Restructuring Responsibility and Reward for More Construction Innovation
This paper proposes modifications to the contractual systems customary in the U.S. construction industry with the objective of encouraging technology innovation. The relationships among...

Partnering: Contracting for Quality
The concept of partnering is an approach to conducting business that confronts the economic and technological challenges confronting the U.S. Construction Industry in the 1990's....

Ahead of Schedule, Under Budget, and Out of Court
The process of designing and constructing facilities involves three parties, the Owner, the Designer and the Constructor. Each has a significant role in this process if the project is...

The Strategy of Bidding for Profit
The ultimate goal of any contractor engaged in competitive bidding is to achieve the maximum profits possible on the jobs he bids, under the prevailing competitive conditions. By systematically...

 

 

 

 

Return to search