Planning and Designing the Powerplant at Stampede Dam

by James C. Conwell, Bureau of Reclamation, Sacramento, CA, USA,
Jerry B. Hammons, Bureau of Reclamation, Sacramento, CA, USA,



Document Type: Proceeding Paper

Part of: Waterpower '85

Abstract:

Power development at Stampede Dam was complicated due to the uncertainty about future reservoir operation and the need to design for seismic risk while attempting to minimize overall cost. This paper reviews the title subject in terms of alternative plans, sizing studies, site conditions, and other related topics.



Subject Headings: Seismic design | Power plants | Hydro power | Reservoirs | Seismic tests | Feasibility studies | Seismic effects

Services: Buy this book/Buy this article

 