McNary Dam - Coordination of Project Design and Construction

by O.R. Lunn,


Serial Information: Journal of the Power Division, 1956, Vol. 82, Issue 2, Pg. 1-8


Document Type: Journal Paper

Abstract:

Four basic factors controlling overall scheduling: navigation; frequency and magnitude of annual floods; temporary fish passage; power on line requirement.



Subject Headings: Dams | Infrastructure construction | Flood frequency | Scheduling | Navigation (geomatic) | Fish management