Rationale of Contract Awards and Contract Systems

by Purushottam S. Gore, Executive Engr.; Maharashtra State Road Transport Corp., Pune, India,


Serial Information: Journal of the Construction Division, 1980, Vol. 106, Issue 4, Pg. 507-518


Document Type: Journal Paper

Errata: (See full record)

Abstract: Choice of proper contractor and contract system can control completion cost and completion time. A method to decide which tender is really economical has developed after a study of twenty-five representative tenders. In any tender, if the rates of items whose quantities are likely to vary considerably on the higher side are high the lowest tender may prove to be the most uneconomical. The method evolved nullifies this effect and gives the acceptable cost level of a tender. The criticality of any item is based on the cost thereof while deciding critical and normal activities.

Subject Headings: Control systems | Contractors and subcontractors | Economic factors | Awards and prizes

Services: Buy this book/Buy this article

 

Return to search